Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Mechanical permit Date: November 1, 2010 Client: Brown Maria B | Permit status: Completed | Permit id: 309450 | |||||
Electrical permit Date: May 3, 2010 Client: Brown Maria B | Permit status: Completed | Permit id: 276533 | |||||
Zoning permit Date: August 7, 2009 Client: Brown Maria B | Permit status: Completed | Permit id: 157046 | |||||
Addition permit Date: August 7, 2009 Client: Brown Maria B | Permit status: Completed | Permit id: 201508 | |||||
Plumbing permit Date: April 30, 2010 Client: Brown Maria B | Permit status: Completed | Permit id: 276121 | |||||
Permit for the erection of a third floor addition and two story side yard addition. Date: July 25, 2008 Client: Brown Maria B | Applicant: Maria Brown | Permit type: Appeal | Permit status: Granted | Permit id: 6237 | |||||
Addition permit Date: August 7, 2009 Client: Brown Maria B | Permit status: Completed | Permit id: 201508 | |||||
Mechanical permit Date: November 1, 2010 Client: Brown Maria B | Permit status: Completed | Permit id: 309450 | |||||
Zoning permit Date: August 7, 2009 Client: Brown Maria B | Permit status: Completed | Permit id: 157046 | |||||
Electrical permit Date: May 3, 2010 Client: Brown Maria B | Permit status: Completed | Permit id: 276533 | |||||
Plumbing permit Date: April 30, 2010 Client: Brown Maria B | Permit status: Completed | Permit id: 276121 | |||||
Permit for the erection of a third floor addition and two story side yard addition. Date: July 25, 2008 Client: Brown Maria B | Applicant: Maria Brown | Permit type: Appeal | Permit status: Granted | Permit id: 6237 | |||||
Rect 3rd story addition and 2 story side yard addition Date: August 7, 2009 Client: Brown Maria B | Permit type: Zoning permit | Permit status: Completed | Completion date: June 3, 2010 | Permit id: 157046 | |||||
Third story addition and rear addition Date: August 7, 2009 Client: Brown Maria B | Permit type: Addition permit | Permit status: Completed | Completion date: January 3, 2011 | Permit id: 201508 | |||||
SCORE 100 Install stack and waste line for 1wc,1 lav sink,1 bath tub Date: April 30, 2010 Contractor: Norman Cole Sr, Client: Brown Maria B | Permit type: Plumbing permit | Permit status: Completed | Completion date: November 1, 2010 | Permit id: 276121 | |||||
SCORE 89 2 amp meter panel, circuit breaker panel, ground rod and ground wiring as per 2008 nec (west dist) Date: May 3, 2010 Contractor: Hooks Earl Client: Brown Maria B | Permit type: Electrical permit | Permit status: Completed | Completion date: December 2, 2010 | Permit id: 276533 | |||||
SCORE 96 Install 90,0 btu gas fired warm air furnace. 3 ton ac unit in yard. All associated ductwork included. Date: November 1, 2010 Contractor: Alexander Pitts Client: Brown Maria B | Permit type: Mechanical permit | Permit status: Completed | Completion date: December 28, 2010 | Permit id: 309450 |