Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 95 Replace fence along western property line. Fence to be 6-feet in height, 200-feet in length, cedar with steel posts. Date: June 1, 2006 Contractor: S C Holley Construction Inc Client: Of City | Applicant: S C Holley Construction Inc | Permit type: Fence | Permit status: Cmp | Completion date: July 24, 2006 | Current use: Multifamily dwe | |||||
SCORE 95 Partial tear off and overlay of epdm roof. 2 sq. Date: August 25, 2006 Contractor: S C Holley Construction Inc Client: Of City | Applicant: S C Holley Construction Inc | Permit type: Roofing | Permit status: Cmp | Completion date: November 29, 2006 | Current use: Multifamily dwe | |||||
SCORE 95 4 - 2" firelines & 1 - 4" fireline to serve diagonal court apts (3265,3267. 3269. 3271 & 3273 30th street) Date: August 23, 2002 Contractor: Valley Excavating Inc Client: Of City | Applicant: Valley Excavating, Inc. | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 100 Fire monitoring system - bldg. D Date: October 29, 2002 Contractor: Safe Systems Inc Client: Of City | Applicant: Safe Systems Inc. | Permit type: Fire | Permit status: Cmp | Completion date: December 3, 2002 | Current use: Multifamily dwe | |||||
SCORE 95 New 2" fireline tap the permit and inspection fees were assessed to pmt2002-2002-02947 Date: August 12, 2002 Contractor: Valley Excavating Inc Client: Of City | Applicant: Valley Excavating, Inc. | Permit type: Water | Permit status: Act | |||||
SCORE 95 Fire sprinkler system (bldg. D) Date: July 31, 2002 Contractor: Western States Fire Protection Client: City Of Boulder Housing Authority | Applicant: Western States Fire Protection | Permit type: Fire | Permit status: Cmp | Completion date: December 3, 2002 | Current use: Multifamily dwe | |||||
SCORE 95 Fire sprinkler system - bld. A Date: July 31, 2002 Contractor: Western States Fire Protection Client: City Of Boulder Housing Authority | Applicant: Western States Fire Protection | Permit type: Fire | Permit status: Cmp | Completion date: December 3, 2002 | Current use: Multifamily dwe | |||||
SCORE 95 4" & 6" firelines (diagonal court apts.) Date: July 29, 2002 Contractor: Valley Excavating Inc Client: Of City | Applicant: Valley Excavating, Inc. | Permit type: Right-of-way | Permit status: N&v | |||||
SCORE 100 New 6" fireline tap will serve 3 buildings a,b, &c with a 2" fire line per building Date: July 15, 2002 Contractor: Of City Client: Of City | Applicant: Of City | Permit type: Water | Permit status: Act | |||||
SCORE 98 Replace forced air furnace. Date: November 29, 2000 Contractor: Cooper Heating And Cooling Inc Client: City Of Boulder | Applicant: Cooper Heating & Cooling Inc | Permit type: Mechanical | Permit status: Cmp | Completion date: May 10, 2001 | Current use: Multifamily dwe | |||||
SCORE 95 Mechanical permit for unit space heaters units 1, 3, 5. Date: July 17, 2007 Contractor: Welzig Mechanical Client: Of City | Applicant: Welzig Mechanical | Permit type: Mechanical | Permit status: Cmp | Completion date: December 31, 2008 | Current use: Multifamily dwe | |||||
SCORE 82 Installation of grid-tied, flushmounted rooftop photovoltaic solar system for 6 unit multi-family building, 1. 75 kw per unit. Date: January 7, 2008 Contractor: Custom Electric Geoff Vezzetti Client: Of City | Applicant: Custom Electric- Geoff Vezzetti | Permit type: Photovoltaic | Permit status: Cmp | Completion date: February 19, 2008 | Current use: Multifamily dwe | |||||
SCORE 100 Installation of a 180,0 btu on-demand water heater and related gas piping in unit 3 to replace an electric water heater.) gas schematic to be provided at rough inspection. No electrical work under the scope of this permit. ( "plug in" electrical water heater and "plug-in" cord for the "on-demand" water heater.) Date: April 16, 2008 Contractor: Utopia Mechanical Inc Client: Of City | Applicant: Utopia Mechanical, Inc. | Permit type: Mechanical | Permit status: Cmp | Completion date: May 12, 2008 | Current use: Multifamily dwe | |||||
SCORE 79 Installation of a 180,0 btu on-demand water heater and related gas piping in unit 1 (to replace an electric water heater.) gas schematic to be provided at rough inspection. No electrical work under the scope of this permit. ( existing "plug in" electrical water heater to be removed and there is a "plug-in" cord for the "on-demand" water heater.) Date: April 29, 2008 Contractor: Independent Home Living Contractors Client: Of City, Boulder Housing Partners | Applicant: Independent Home Living Contractors | Permit type: Mechanical | Permit status: Cmp | Completion date: May 6, 2008 | Current use: Multifamily dwe | |||||
SCORE 79 Installation of a 180,0 btu on-demand water heater and related gas piping in unit 2 (to replace an electric water heater.) gas schematic to be provided at rough inspection. No electrical work under the scope of this permit. ( existing "plug in" electrical water heater to be removed and there is a "plug-in" cord for the "on-demand" water heater.) Date: April 29, 2008 Contractor: Independent Home Living Contractors Client: Of City, Boulder Housing Partners | Applicant: Independent Home Living Contractors | Permit type: Mechanical | Permit status: Cmp | Completion date: May 6, 2008 | Current use: Multifamily dwe | |||||
SCORE 79 Installation of a 180,0 btu on-demand water heater and related gas piping in unit 4 (to replace an electric water heater.) gas schematic to be provided at rough inspection. No electrical work under the scope of this permit. ( existing "plug in" electrical water heater to be removed and there is a "plug-in" cord for the "on-demand" water heater.) Date: April 29, 2008 Contractor: Independent Home Living Contractors Client: Boulder Housing Partners, City Of Boulder | Applicant: Independent Home Living Contractors | Permit type: Mechanical | Permit status: Cmp | Completion date: May 6, 2008 | Current use: Multifamily dwe | |||||
SCORE 79 Installation of a 180,0 btu on-demand water heater and related gas piping in unit 5 (to replace an electric water heater.) gas schematic to be provided at rough inspection. No electrical work under the scope of this permit. ( existing "plug in" electrical water heater to be removed and there is a "plug-in" cord for the "on-demand" water heater.) Date: April 29, 2008 Contractor: Independent Home Living Contractors Client: Boulder Housing Partners, City Of Boulder | Applicant: Independent Home Living Contractors | Permit type: Mechanical | Permit status: Cmp | Completion date: May 12, 2008 | Current use: Multifamily dwe | |||||
SCORE 79 Installation of a 180,0 btu on-demand water heater and related gas piping in unit 6 (to replace an electric water heater.) gas schematic to be provided at rough inspection. No electrical work under the scope of this permit. ( existing "plug in" electrical water heater to be removed and there is a "plug-in" cord for the "on-demand" water heater.) Date: April 29, 2008 Contractor: Independent Home Living Contractors Client: Boulder Housing Partners, City Of Boulder | Applicant: Independent Home Living Contractors | Permit type: Mechanical | Permit status: Cmp | Completion date: May 12, 2008 | Current use: Multifamily dwe | |||||
SCORE 95 Replacement forced air furnace for unit 6. 45k btu. Date: October 28, 2009 Contractor: Welzig Mechanical Client: Of City | Applicant: Welzig Mechanical | Permit type: Mechanical | Permit status: Cmp | Completion date: June 9, 2011 | Current use: Multifamily dwe | |||||
SCORE 95 Building 3265 30th st. (bldg. A, 6 units). Addition (16 sq. Ft. Per unit) and remodel (4 sq. Ft. Per unit to include the conversion of laundry room in bldg. C to administrative offices). Scope of work includes new skylights and associated meps to include ventilating equipment. Proposed community center under separate permit and any sitework, signage, walls, and fire sprinkling work under separate permit if necessary. See lur2015-00031 approval. Client: Of City | Applicant: Palace Construction Co Inc | Permit type: Building, electrical | Permit status: Def | Current use: Multifamily dwe | |||||
SCORE 95 Fs - sowl - add 2 spks and relocate 1 Client: Communitie Boulder | Permit type: Fire | Permit status: Cmp | Completion date: August 12, 2016 | Current use: Multifamily dwellings, existing | Permit id: Pmt2016-00431 | |||||
SCORE 95 Fa - new system and for clubhouse Client: Communitie Boulder | Permit type: Fire | Permit status: N&v | Current use: Multifamily dwellings, existing | Permit id: Pmt2016-00523 | |||||
SCORE 76 Fa - es - new sytem and addition of community room Client: Communitie Boulder | Permit type: Fire | Permit status: Cmp | Completion date: September 8, 2016 | Current use: Multifamily dwellings, existing | Permit id: Pmt2016-00684 | |||||
SCORE 95 Tap install new fireline, associated with building permit pmt2015-03863 Date: March 11, 2016 Contractor: Randy Kneebone Excavatingtrucking Client: Communitie Boulder | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2016-01063 | |||||
SCORE 95 Tap install 1inch irrigation meter & pit, 1inch domestic, associated with building pmt2015-03863 Date: April 21, 2016 Contractor: Golden West Plumbing, Heating And Ac Client: Communitie Boulder | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2016-01689 | |||||
SCORE 95 Fa - es - aes 7788f radio Client: Communitie Boulder | Permit type: Fire | Permit status: Cmp | Completion date: September 14, 2016 | Current use: Multifamily dwellings, existing | Permit id: Pmt2016-03042 | |||||
Bore 210foot for new svc. All work is on private property. Job #39902 Date: July 25, 2016 Client: Communitie Boulder | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2016-03410 | |||||
SCORE 100 New 17. 33 kw pv system of the newly constructed community center addition (see pmt2015-03863.) Client: Communitie Boulder | Permit type: Photovoltaic | Permit status: Cmp | Completion date: November 2, 2016 | Current use: Amusement/recreational - indoor, existin | Permit id: Pmt2016-04649 | |||||
SCORE 95 Replacement forced air furnace for unit 6. 45k btu. Client: Of City | Permit type: Mechanical | Permit status: Cmp | Completion date: June 9, 2011 | Current use: Multifamily dwellings, existing | Permit id: Pmt2009-04371 | |||||
New 6" fireline tap will serve 3 buildings a,b, &c with a 2" fire line per building Client: Of City | Permit type: Water | Permit status: Act | Permit id: Pmt2002-02947 | |||||
SCORE 100 Fire monitoring system - bldg. D Client: Of City | Permit type: Fire | Permit status: Cmp | Completion date: December 3, 2002 | Current use: Multifamily dwellings, existing | Permit id: Pmt2002-04708 | |||||
SCORE 95 Building 3265 30th st. (bldg. A, 6 units). Addition of approximately 4,453 sq ft for a new community center. Addition to existing portion of building (16 sq. Ft. Per unit) and remodel. Scope of work includes new skylights and associated meps to include ventilating equipment. Scope will include all associated mepfoots for the center addition as well as additons of front porches with trellises and rear porches with tellises and storage areas, to the existing (6) dwelling units. Client: Of City | Permit type: Building, electrical, mechanical, plumbing, fire, water, wastewater, sitework | Permit status: Cmp | Completion date: October 18, 2016 | Current use: Office - administrative, addition | Permit id: Pmt2015-03863 | |||||
SCORE 95 Fs - sowl - add 2 and relocate 1 Client: Communitie Boulder | Permit type: Fire | Permit status: Cmp | Completion date: September 8, 2016 | Current use: Multifamily dwellings, existing | Permit id: Pmt2015-05551 | |||||
SCORE 95 Partial tear off and overlay of epdm roof. 2 sq. Client: Of City | Permit type: Roofing | Permit status: Cmp | Completion date: November 29, 2006 | Current use: Multifamily dwellings, existing | Permit id: Pmt2006-03558 | |||||
SCORE 98 Replace forced air furnace. Client: City Of Boulder | Permit type: Mechanical | Permit status: Cmp | Completion date: May 10, 2001 | Current use: Multifamily dwellings, existing | Permit id: Pmt2000-04848 | |||||
New 6inch fireline tap will serve 3 buildings a,b, &c with a 2inch fire line per building Client: Of City | Permit type: Water | Permit status: Act | Permit id: Pmt2002-02947 | |||||
SCORE 95 4inch & 6inch firelines (diagonal court apts.) Date: July 29, 2002 Contractor: Valley Excavating, Inc Client: Of City | Permit type: Right-of-way | Permit status: N&v | Permit id: Pmt2002-03166 | |||||
SCORE 95 Fire sprinkler system - bld. A Client: City Of Boulder Housing Authority | Permit type: Fire | Permit status: Cmp | Completion date: December 3, 2002 | Current use: Multifamily dwellings, existing | Permit id: Pmt2002-03260 | |||||
SCORE 95 Fire sprinkler system (bldg. D) Client: City Of Boulder Housing Authority | Permit type: Fire | Permit status: Cmp | Completion date: December 3, 2002 | Current use: Multifamily dwellings, existing | Permit id: Pmt2002-03265 | |||||
SCORE 95 New 2inch fireline tap the permit and inspection fees were assessed to pmt2002-2002-02947 Contractor: Valley Excavating, Inc Client: Of City | Permit type: Water | Permit status: Act | Permit id: Pmt2002-03467 | |||||
SCORE 95 4 - 2inch firelines & 1 - 4inch fireline to serve diagonal court apts (3265,3267. 3269. 3271 & 3273 30th street) Date: August 23, 2002 Contractor: Valley Excavating, Inc Client: Of City | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2002-03680 | |||||
SCORE 95 Replace fence along western property line. Fence to be 6-feet in height, 200-feet in length, cedar with steel posts. Client: Of City | Permit type: Fence | Permit status: Cmp | Completion date: July 24, 2006 | Current use: Multifamily dwellings, existing | Permit id: Pmt2006-02110 | |||||
SCORE 95 Partial tear off and overlay of epdm roof. 2 sq. Value: $800 Contractor: S C Holley Construction Inc Client: Of City | Permit type: Roofing | Permit status: Act | Current use: Multifamily dwellings, existing | Permit id: Pmt2006-03559 | |||||
SCORE 95 Mechanical permit for unit space heaters units 1, 3, 5. Client: Of City | Permit type: Mechanical | Permit status: Cmp | Completion date: December 31, 2008 | Current use: Multifamily dwellings, existing | Permit id: Pmt2007-02967 | |||||
SCORE 82 Installation of grid-tied, flushmounted rooftop photovoltaic solar system for 6 unit multi-family building, 1. 75 kw per unit. Client: Of City | Permit type: Photovoltaic | Permit status: Cmp | Completion date: February 19, 2008 | Current use: Multifamily dwellings, existing | Permit id: Pmt2008-00046 | |||||
SCORE 100 Installation of a 180,0 btu on-demand water heater and related gas piping in unit 3 to replace an electric water heater.) gas schematic to be provided at rough inspection. No electrical work under the scope of this permit. ( inchplug ininch electrical water heater and inchplug-ininch cord for the inchon-demandinch water heater.) Client: Of City | Permit type: Mechanical | Permit status: Cmp | Completion date: May 12, 2008 | Current use: Multifamily dwellings, existing | Permit id: Pmt2008-01436 | |||||
SCORE 79 Installation of a 180,0 btu on-demand water heater and related gas piping in unit 1 (to replace an electric water heater.) gas schematic to be provided at rough inspection. No electrical work under the scope of this permit. ( existing inchplug ininch electrical water heater to be removed and there is a inchplug-ininch cord for the inchon-demandinch water heater.) Client: Of City | Permit type: Mechanical | Permit status: Cmp | Completion date: May 6, 2008 | Current use: Multifamily dwellings, existing | Permit id: Pmt2008-01611 | |||||
SCORE 79 Installation of a 180,0 btu on-demand water heater and related gas piping in unit 2 (to replace an electric water heater.) gas schematic to be provided at rough inspection. No electrical work under the scope of this permit. ( existing inchplug ininch electrical water heater to be removed and there is a inchplug-ininch cord for the inchon-demandinch water heater.) Client: Of City | Permit type: Mechanical | Permit status: Cmp | Completion date: May 6, 2008 | Current use: Multifamily dwellings, existing | Permit id: Pmt2008-01612 | |||||
SCORE 79 Installation of a 180,0 btu on-demand water heater and related gas piping in unit 4 (to replace an electric water heater.) gas schematic to be provided at rough inspection. No electrical work under the scope of this permit. ( existing inchplug ininch electrical water heater to be removed and there is a inchplug-ininch cord for the inchon-demandinch water heater.) Client: Boulder Housing Partners | Permit type: Mechanical | Permit status: Cmp | Completion date: May 6, 2008 | Current use: Multifamily dwellings, existing | Permit id: Pmt2008-01613 | |||||
SCORE 79 Installation of a 180,0 btu on-demand water heater and related gas piping in unit 5 (to replace an electric water heater.) gas schematic to be provided at rough inspection. No electrical work under the scope of this permit. ( existing inchplug ininch electrical water heater to be removed and there is a inchplug-ininch cord for the inchon-demandinch water heater.) Client: Boulder Housing Partners | Permit type: Mechanical | Permit status: Cmp | Completion date: May 12, 2008 | Current use: Multifamily dwellings, existing | Permit id: Pmt2008-01614 | |||||
SCORE 79 Installation of a 180,0 btu on-demand water heater and related gas piping in unit 6 (to replace an electric water heater.) gas schematic to be provided at rough inspection. No electrical work under the scope of this permit. ( existing inchplug ininch electrical water heater to be removed and there is a inchplug-ininch cord for the inchon-demandinch water heater.) Client: Boulder Housing Partners | Permit type: Mechanical | Permit status: Cmp | Completion date: May 12, 2008 | Current use: Multifamily dwellings, existing | Permit id: Pmt2008-01616 | |||||
SCORE 95 Building 3265 30th st. (bldg. A, 6 units). Addition (16 sq. Ft. Per unit) and remodel (4 sq. Ft. Per unit to include the conversion of laundry room in bldg. C to administrative offices). Scope of work includes new skylights and associated meps to include ventilating equipment. Proposed community center under separate permit; signage, walls, and fire sprinkling work under separate permit if necessary. See lur2015-00031 approval. Site work and landscape is included per the approved tec doc (tec2015-00042). Value: $445,968 Contractor: Palace Construction Co Inc Client: City Of Boulder Hsg Authority | Permit type: Building, electrical, mechanical, plumbing, siding | Permit status: N&v | Current use: Multifamily dwellings, addition and remo | Permit id: Pmt2015-03591 | |||||
SCORE 76 Fa - es - new ifp- spk monitor and notification Contractor: Adk Electric Corporation Client: Communitie Boulder | Permit type: Fire | Permit status: Act | Current use: Office - administrative, existing | Permit id: Pmt2016-00429 |