Plumbing permit Date: April 20, 2012 Client: Tbm Group Inc | Permit status: Completed | Permit id: 400612 | |||||
Mechanical permit Date: May 2, 2012 Client: Tbm Group Inc | Permit status: Completed | Permit id: 402821 | |||||
Zoning permit Date: February 18, 2014 Client: Wilson Kristen Ellen Wilson John | Permit status: Completed | Permit id: 513907 | |||||
Electrical permit Date: June 15, 2012 Client: Tbm Group Inc | Permit status: Completed | Permit id: 411298 | |||||
Zoning use permit Date: March 5, 2012 Client: Tbm Group Inc | Permit status: Completed | Permit id: 371279 | |||||
Alteration permit Date: June 21, 2013 Client: Wilson Kristen Ellen Wilson John | Permit status: Completed | Permit id: 478998 | |||||
New construction permit Date: March 15, 2012 Client: Tbm Group Inc | Permit status: Completed | Permit id: 392410 | |||||
Suppression permit Date: May 18, 2012 Client: Tbm Group Inc | Permit status: Completed | Permit id: 403192 | |||||
Use permit Date: August 31, 2012 Client: Tbm Group Inc | Permit status: Completed | Permit id: 419878 | |||||
Electrical permit Date: August 30, 2013 Client: Wilson Kristen Ellen Wilson John | Permit status: Completed | Permit id: 492285 | |||||
Permit for the erection of a three (3) story attached structure (not to exceed thirty-five feet (35-0") in height) with partial roof top deck accessed by a pilot house at the roof level (pilot house footprint not to exceed forty-eight square feet (48 sf); height not to exceed ten feet (100")). Proposed structure for use as a two (2) family dwelling throughout. For the erection of six foot (6-0") high fencing in the rear yard. For the elimination of a sixteen foot (16-0") wide rear driveway easement previously established on zoning permit # 347369 and use permit # 347370. Date: January 3, 2012 Client: Tbm Group Inc | Applicant: Joseph Beller, Esq. | Permit type: Appeal | Permit status: Granted/prov | Completion date: February 28, 2012 | Permit id: 16945 | |||||
SCORE 100 Installed 4 gfci wall outlets installed 2 wall switches 3 light fixtures,2 pull chain fixtures,3 wall outlets per 2008 nec (sfd) Date: August 30, 2013 Contractor: Christopher Richard Client: Wilson Kristen Ellen Wilson John | Permit type: Electrical permit | Permit status: Completed | Completion date: April 8, 2014 | Permit id: 492285 | |||||
SCORE 92 Remove all kitchen cabinets, bathroom fixtures (2 bathrooms, wall down to studs new sheet rock on bathrooms, remove 2 closets non load bearing - additional permits are required for electrical, plumbing Date: June 21, 2013 Contractor: J L Ramos And Associates Inc Client: Wilson Kristen Ellen Wilson John | Permit type: Alteration permit | Permit status: Completed | Completion date: July 3, 2014 | Permit id: 478998 | |||||
For the creation of one (1) accessory open-air off street parking space in the rear yard of an existing three story structure for a two family dwelling.. No alterations to existing bldg. Street department approval required prior to issuance of building permit. Date: August 31, 2012 Client: Tbm Group Inc | Permit type: Use permit | Permit status: Completed | Completion date: August 31, 2012 | Permit id: 419878 | |||||
SCORE 100 1 new 200amp service and 3 meter sockets all interior wiring per 2008 nec Date: June 15, 2012 Contractor: Tech Electric Services Inc Client: Tbm Group Inc | Permit type: Electrical permit | Permit status: Completed | Completion date: October 5, 2012 | Permit id: 411298 | |||||
SCORE 100 For the installation of a two (2) inch fire service line with backflow preventor (bfp) assembly for a two (2) family dwelling; fire sprinkler system installation in accordance with nfpa 13r. Installation of fire sprinkler piping, sprinkler heads, & related piping appurtenances to be performed by a licensed fire suppression contractor in accordance with the philadelphia fire code. Date: May 18, 2012 Contractor: B. M. Consulting Services Inc Client: Tbm Group Inc | Permit type: Suppression permit | Permit status: Completed | Completion date: November 28, 2012 | Permit id: 403192 | |||||
SCORE 100 Install 2 heat pumps (duplex) see new construction permit #392410 Date: May 2, 2012 Contractor: Talgar Inc Client: Tbm Group Inc | Permit type: Mechanical permit | Permit status: Completed | Completion date: November 28, 2012 | Permit id: 402821 | |||||
SCORE 100 Install sewer lateral from main to bldg(2fd) Date: April 25, 2012 Contractor: Benjamin Magness Client: Tbm Group Inc | Permit type: Plumbing permit | Permit status: Completed | Completion date: November 28, 2012 | Permit id: 401293 | |||||
SCORE 97 Install 2 toilets, 2 bath tubs, 2 lav sinks, 2 ks, 2 laundry waste pipes and 2 water heaters(2fd) Date: April 20, 2012 Contractor: Richard Lawrence Client: Tbm Group Inc | Permit type: Plumbing permit | Permit status: Completed | Completion date: November 28, 2012 | Permit id: 400612 | |||||
New construction of a new 2 family dwelling each with cellar and basement Date: March 15, 2012 Client: Tbm Group Inc | Permit type: New construction permit | Permit status: Completed | Completion date: November 28, 2012 | Permit id: 392410 | |||||
For the erection of a 3 story two family dwelling with cellar & roof deck and installation of 6ft high fence in side and rear of property. Date: March 5, 2012 Client: Tbm Group Inc | Permit type: Zoning/use permit | Permit status: Completed | Completion date: March 5, 2012 | Permit id: 371279 |