Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 64 Temp use application for fireworks stand. Fire dept approval required. Date: May 30, 2014 Contractor: Jakes Fireworksjakes Fireworks @ Costco Permit type: Temporary use | Permit status: Completed | Completion date: June 2, 2014 | Permit id: Bld2014-03751 | |||||
SCORE 79 To change refrigerated fixtures (meat & deli section) Date: January 14, 2015 Permit type: Mechanical | Permit status: Accepted | Completion date: January 14, 2015 | Current use: Commercial | Permit id: Bld2015-00274 | |||||
SCORE 79 Hard wire refrigerated fixtures (meat & deli section) Date: January 14, 2015 Permit type: Electrical | Permit status: In progress | Completion date: January 14, 2015 | Current use: Commercial | Permit id: Bld2015-00275 | |||||
SCORE 64 The project is a 69,636sf building addition to a one story mercantile occupancy. Separate permits required for elec, mech, plmb. Fire inspections. Date: March 2, 2015 Permit type: Permit | Permit status: Completed | Completion date: June 18, 2015 | Current use: Commercial | Permit id: Bld2015-01358 | |||||
SCORE 79 6-a/c Date: March 3, 2015 Permit type: Mechanical | Permit status: Accepted | Completion date: March 3, 2015 | Current use: Commercial | Permit id: Bld2015-01395 | |||||
SCORE 64 Walk in cooler expansion on the interior of the existing retail space. Electrical and plumbing permits required. Date: March 12, 2015 Contractor: Uintah Refrigeration And Electrical Llccostco Permit type: Permit | Permit status: Accepted - standard | Completion date: March 12, 2015 | Current use: Commercial | Permit id: Bld2015-01608 | |||||
SCORE 64 Billboard demo Date: March 17, 2015 Contractor: R. O. A. General Inccostco Wholesale Corp Permit type: Sign | Permit status: Pass | Completion date: June 4, 2015 | Permit id: Bld2015-01704 | |||||
SCORE 74 Expansion of existing facility Date: June 4, 2015 Contractor: Wilkinson Electriccostco Wholesale Expansion Permit type: Electrical | Permit status: Accepted | Completion date: June 5, 2015 | Current use: Commercial | Permit id: Bld2015-03928 | |||||
SCORE 74 Electrical and power to panel are arthourized by separate permits. Temporary power Date: June 4, 2015 Contractor: Wilkinson Electriccostco Wholesale Expansion Permit type: Electrical | Permit status: Completed | Completion date: June 5, 2015 | Current use: Commercial | Permit id: Bld2015-03967 | |||||
SCORE 64 Install plumbing Date: June 23, 2015 Contractor: Rk Mechanicalcostco Depot Addition Permit type: Plumbing | Permit status: Reviews not require | Completion date: June 23, 2015 | Current use: Commercial | Permit id: Bld2015-04561 | |||||
SCORE 64 Fire line and 2 hydrants Date: June 26, 2015 Contractor: Staker And Parson Companiescostco Permit type: Fire | Permit status: Closed | Completion date: July 20, 2015 | Current use: Commercial | Permit id: Bld2015-04713 | |||||
SCORE 64 The fire alarm plans for the costco retail store in salt lake city Date: July 8, 2015 Contractor: Wiretechcostco Fire Alarm Permit type: Fire | Permit status: Accepted - login review | Completion date: July 8, 2015 | Current use: Commercial | Permit id: Bld2015-05096 | |||||
SCORE 64 Addition to existing costco store Date: July 15, 2015 Contractor: Costco Addition Permit type: Fire | Permit status: Accepted - login review | Completion date: July 16, 2015 | Current use: Commercial | Permit id: Bld2015-05343 | |||||
SCORE 64 Furnish and install 2 each exhaust fans and 2 each transfer fans and ductwork. Install ductwork for owner furnished equipment. Date: July 16, 2015 Contractor: Sheet Metal Systems Inccostco Warehouse Slc Permit type: Mechanical | Permit status: Reviews not require | Completion date: July 16, 2015 | Current use: Commercial | Permit id: Bld2015-05426 | |||||
SCORE 64 Fuel additive retrofit, mech & elec permits reqd k. A. K. B. D. W. Date: March 27, 2012 Permit type: Permit | Permit status: Completed | Completion date: June 7, 2012 | Current use: Commercial | Permit id: Bld2012-02262 | |||||
SCORE 64 Switchgear replacement. Date: March 8, 2011 Contractor: Hunt Electriccostco Wholesale Corporation Permit type: Electrical | Permit status: Pass | Completion date: May 3, 2011 | Current use: Commercial | Permit id: Bld2011-01345 | |||||
SCORE 64 Tube heater Date: February 22, 2011 Contractor: James M Ballcostco Wholesale Corporation Permit type: Mechanical | Permit status: Pass | Completion date: February 28, 2011 | Current use: Commercial | Permit id: Bld2011-01087 | |||||
SCORE 64 Elec work for installation of 12 gallon above ground storage tank. Date: November 15, 2010 Contractor: Cedar Ridge Electric Llccostco Gasoline Permit type: Electrical | Permit status: Pass | Completion date: November 23, 2010 | Current use: Commercial | Permit id: Bld2010-07872 | |||||
Installation of 12 gallon above ground storage tank. Date: August 31, 2010 Permit type: Permit | Permit status: Pass | Completion date: November 29, 2010 | Current use: Commercial | Permit id: Bld2010-05988 | |||||
SCORE 64 Fire sprinkler system for cooler Date: September 3, 2009 Contractor: Quality Fire Protection Inccostco Wholesale Permit type: Fire | Permit status: Pass | Completion date: March 9, 2012 | Current use: Commercial | Permit id: Bld2009-05363 | |||||
Install refrigated floral cooler Date: July 22, 2009 Permit type: Permit | Permit status: Pass | Completion date: March 13, 2012 | Current use: Residential | Permit id: Bld2009-04305 | |||||
SCORE 81 Commercial electrical for new costco Date: October 5, 2015 Contractor: Staybright Electric Of Colorado Inc Permit type: Electrical | Permit status: Inspections | Completion date: October 5, 2015 | Current use: Commercial | Permit id: Bld2015-08163 |