Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Mechanical permit Date: November 29, 2012 Permit status: Completed | Permit id: 440444 | |||||
New construction permit Date: November 16, 2012 Permit status: Completed | Permit id: 436358 | |||||
Plumbing permit Date: November 13, 2012 Permit status: Completed | Permit id: 437659 | |||||
Zoning/use permit Date: October 18, 2012 Permit status: Completed | Permit id: 430942 | |||||
Electrical permit Date: December 3, 2012 Permit status: Completed | Permit id: 441224 | |||||
Suppression permit Date: February 7, 2013 Permit status: Completed | Permit id: 442386 | |||||
Zoning use permit Date: September 13, 2012 Permit status: Completed | Permit id: 425717 | |||||
Electrical permit Date: December 3, 2012 Permit status: Completed | Permit id: 441224 | |||||
Suppression permit Date: February 7, 2013 Permit status: Completed | Permit id: 442386 | |||||
Mechanical permit Date: November 29, 2012 Permit status: Completed | Permit id: 440444 | |||||
New construction permit Date: October 26, 2012 Permit status: Completed | Permit id: 434287 | |||||
Plumbing permit Date: December 3, 2012 Permit status: Completed | Permit id: 441191 | |||||
New construction of a triplex. Date: September 13, 2012 Permit type: Zoning/use permit | Permit status: Completed | Completion date: September 13, 2012 | Permit id: 425717 | |||||
Reduce number of stories from (4) to (3) to be used as a duplex. Date: October 18, 2012 Permit type: Zoning/use permit | Permit status: Completed | Completion date: October 18, 2012 | Permit id: 430942 | |||||
SCORE 96 Install foundation only as per plans for an attached 2-family dwelling in accordance with 2009 ibc and ploans approved under ap #434282, Date: October 26, 2012 Contractor: Msj Contractors Llc Permit type: New construction permit | Permit status: Completed | Completion date: February 19, 2013 | Permit id: 434287 | |||||
For the erection of a three story attached structure with cellar for use as a two family dwelling. All work shall comply with the approved plans. This work actvity shall be performed by contractors & sub-contractors licensed by the city of philadelphia. This structure is fully sprinklered; nfpa 13r system. Shared plans #436353 & 436359. Date: November 16, 2012 Permit type: New construction permit | Permit status: Completed | Completion date: February 19, 2013 | Permit id: 436358 | |||||
SCORE 100 Iinstall sanitary drain to all fixtures, water supply to all fixture 2-ks, 2-wm, 4-wc, 4-shower 4-lavs & 2-hwh (2fd) Date: November 13, 2012 Contractor: Drain Masters Plumbing Llc Permit type: Plumbing permit | Permit status: Completed | Completion date: February 19, 2013 | Permit id: 437659 | |||||
SCORE 82 Installation of 2 heat pumps (3 ton goodman). Duplex Date: November 29, 2012 Contractor: Good Deals Heating And Cooling Permit type: Mechanical permit | Permit status: Completed | Completion date: February 19, 2013 | Permit id: 440444 | |||||
SCORE 100 Install a new 5" sewer lateral,install a new 5" curb trap, fresh air inlet, 3 4 water service (2 family ) Date: December 3, 2012 Contractor: Drain Masters Plumbing Llc Permit type: Plumbing permit | Permit status: Completed | Completion date: February 19, 2013 | Permit id: 441191 | |||||
SCORE 100 Install 200a service,100a sub panel, and complete rewire in accordance with 2008 nec(sfd)(north dist) Date: December 3, 2012 Contractor: A One Electric Llc Permit type: Electrical permit | Permit status: Completed | Completion date: January 7, 2016 | Permit id: 441224 | |||||
SCORE 100 For the installation of a one (1) inch fire service line with a backflow preventer assembly for a two family dwelling, fire sprinkler system installation in accordance with nfpa 13r. Date: February 7, 2013 Contractor: Oneida Fire Protection Permit type: Suppression permit | Permit status: Completed | Completion date: February 19, 2013 | Permit id: 442386 |