Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 95 Sewer systems, inlets, downspouts, fire main and water service Date: August 16, 2013 Contractor: David Miller Permit type: Commercial plumbing | Permit status: Issued | Permit id: Plb-13-05643 | |||||
Plumbing fixtures water heater rpz sanitary sewer Date: July 15, 2013 Permit type: Commercial plumbing | Permit status: Issued | Permit id: Plb-13-04819 | |||||
Commercial plumbing Date: August 26, 2013 Permit status: Issued | Permit id: Plb-13-05895 | |||||
SCORE 93 Hawkins-1)above ground 225 gal lube oil tank, 2)above ground 7 gal lube oil tank, 4)above ground 325 gal lube oil tank Date: February 14, 2014 Contractor: William Krajicek Permit type: Flammable liquids tank install | Permit status: Issued | Permit id: Mec-14-01292 | |||||
SCORE 96 Complete electrical installation for a new equipment maintenance building Date: September 26, 2013 Contractor: Thomas Respeliers Permit type: Commercial electrical | Permit status: Issued | Permit id: Elc-13-09968 | |||||
Hawkins maintenance facility - car wash bay Date: April 8, 2014 Permit type: Building - certificate of occupancy | Permit status: Closed | Permit id: Coo-14-00111 | |||||
SCORE 95 Commercial electrical Date: August 8, 2013 Contractor: Patrick Killeen Permit status: Issued | Permit id: Elc-13-08121 | |||||
SCORE 93 Hawkins construction-18-ruskin fire dampers, 17-variable air volume boxes cfm-3000cfm, 7-articulating exhaust arms 350cfm-1800cfm, 23-cook exhaust fans 1 cfm-10000cfm Date: August 30, 2013 Contractor: Blaine Wilcoxson Permit type: Commercial air conditioning air distribution systems | Permit status: Issued | Permit id: Mec-13-07635 | |||||
Hawkins construction company equipment and vehicle maintenance facility | a landscaping bond is on file with mike wilwerding - 02/14/2014 Date: February 19, 2014 Permit type: Building - certificate of occupancy | Permit status: Closed | Permit id: Coo-14-00063 | |||||
SCORE 93 Hawkins-air piping, air compressor tank 107cfm, air dryer 1 scfm, air receiver 2 gal Date: February 14, 2014 Contractor: William Krajicek Permit type: Boilers and pressure vessels | Permit status: Issued | Permit id: Mec-14-01291 | |||||
SCORE 95 Hawkins construction-new maintenance shop. C-10767 Date: August 27, 2013 Contractor: Jason Brown Permit type: Fire sprinkler/chemical/control systems | Permit status: Issued | Permit id: Mec-13-07481 | |||||
SCORE 93 Service station 43246 sf; 2nd lvl offices 9994 sf; Permit type: Plans required - commercial new building | Permit status: Issued | Permit id: Bld-13-02115 | |||||
SCORE 93 Hawkins construction-lochnivar boiler 1500000btuh input Date: September 19, 2013 Contractor: William Krajicek Permit type: Boilers and pressure vessels | Permit status: Issued | Permit id: Mec-13-08180 | |||||
SCORE 95 Hawkins construction-2-exhaust fans, makeup air unit 4752000btuh. 12-3-13 quad fee for paint booth permit. Date: February 12, 2014 Contractor: John Wilhelmi Permit type: Commercial air conditioning air distribution systems | Permit status: Issued | Permit id: Mec-14-01237 | |||||
Hawkins construction company equipment and vehicle maintenance facility | a landscaping bond is on file with mike wilwerding - 02 14 2014 Date: February 19, 2014 Permit type: Building - certificate of occupancy | Permit status: Closed | Permit id: Coo-14-00063 | |||||
SCORE 93 Hawkins construction-piping for in-floor heat & piping for boiler, domestic hws/r plate & frame hx 720000btuh, buffer tank hws/r 115 gal. Date: September 19, 2013 Contractor: William Krajicek Permit type: Hydronic/process/ammonia piping systems | Permit status: Issued | Permit id: Mec-13-08179 |