Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 63 Installation of lineal feet of replacement 6foot high cedar privacy fence along a portion of the east property line. Date: April 17, 2009 Contractor: Laurie Brockway Client: Daniel Brockway,Laurie Brockway | Applicant: Laurie Brockway | Permit type: Fence | Permit status: Cmp | Completion date: August 7, 2014 | |||||
SCORE 95 Sewer service repair in alley. Date: April 21, 2010 Contractor: Pipe X Llc Client: Daniel Brockway,Laurie Brockway | Applicant: Pipe X Llc | Permit type: Wastewater, right-of | Permit status: Iss | |||||
SCORE 95 Remove unit #1 of existing 4 plex and replace with 2 bedrooms and office bedroom, 2. 5 baths, rooftop deck, finished basement, associated electrical, mechanical and plumbing. Client: Daniel Brockway,Laurie Brockway | Applicant: Colorado Choice Builders | Permit type: Building, electrical | Permit status: Iss | Current use: Multifamily dwe | |||||
SCORE 100 Tap install new 3 4inch irrigation meter service, concrete pumper setup, associated with pmt2013-04788 Date: July 2, 2014 Contractor: Cap Excavating Inc Client: Daniel Brockway,Laurie Brockway | Applicant: Cap Excavating, Inc | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 100 Renew gas service via bore Date: October 31, 2014 Contractor: Xcel Energy Client: Daniel Brockway,Laurie Brockway | Applicant: Xcel Energy | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 95 Installation of a flush mount, grid-tied, 6. 87kw photovoltaic system. Array to remain below ridge, inside below hips and rake edges, and above eave. See engineerfoots letter and drawing for specific information. Date: October 31, 2014 Contractor: Namaste Solar Electric Inc Client: Daniel Brockway,Laurie Brockway | Applicant: Namaste Solar Electric Inc | Permit type: Photovoltaic | Permit status: Cmp | Completion date: March 16, 2015 | Current use: Single family d | |||||
SCORE 95 Fs - es - new residential system (13d) Date: November 10, 2014 Contractor: Western States Fire Protection Client: Daniel Brockway,Laurie Brockway | Applicant: Western States Fire Protection | Permit type: Fire | Permit status: Iss | Current use: Single family a | |||||
Installation of lineal feet of replacement 6foot high cedar privacy fence along a portion of the east property line. Date: April 20, 2009 Value: $600 Client: Daniel Brockway | Permit type: Fence | Permit status: Cmp | Completion date: August 7, 2014 | Permit id: Pmt2009-01276 | |||||
SCORE 95 Remove unit #1 of existing 4 plex and replace with 2 bedrooms and office bedroom, 2. 5 baths, rooftop deck, finished basement, associated electrical, mechanical and plumbing. Client: Daniel Brockway | Permit type: Building, electrical, mechanical, plumbing | Permit status: Cmp | Completion date: September 2, 2015 | Current use: Multifamily dwellings, addition | Permit id: Pmt2013-04788 | |||||
SCORE 95 Tap install new 3 4inch irrigation meter service, concrete pumper setup, associated with pmt2013-04788 Date: July 2, 2014 Contractor: Cap Excavating, Inc Client: Daniel Brockway | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2014-03113 | |||||
SCORE 80 Renew gas service via bore Date: October 31, 2014 Contractor: Q3 Contracting, Inc Client: Daniel Brockway | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2014-04810 | |||||
SCORE 95 Installation of a flush mount, grid-tied, 6. 87kw photovoltaic system. Array to remain below ridge, inside below hips and rake edges, and above eave. See engineerfoots letter and drawing for specific information. Client: Daniel Brockway | Permit type: Photovoltaic | Permit status: Cmp | Completion date: March 16, 2015 | Current use: Single family detached dwelling, existin | Permit id: Pmt2014-04976 | |||||
SCORE 95 Fs - es - new residential system (13d) Client: Daniel Brockway | Permit type: Fire | Permit status: Iss | Current use: Single family attached dwelling, existin | Permit id: Pmt2014-05090 |