Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Addition permit Date: December 23, 2016 Permit status: Active | Permit id: 739770 | |||||
Zoning permit Date: December 23, 2016 Permit status: Completed | Permit id: 739769 | |||||
Demolition permit Date: October 14, 2016 Permit status: Completed | Permit id: 729448 | |||||
Alteration permit Date: October 31, 2016 Permit status: Active | Permit id: 733248 | |||||
Electrical permit Date: November 9, 2016 Permit status: Active | Permit id: 735605 | |||||
For the demolition of one story shed and for the erection of an addition to an existing attached structure with a roof deck over the third story portion accessed by a spiral stairway from the third floor level. Structure for use as a single family houshold living. Size and location as shown per application plan. Date: December 23, 2016 Permit type: Zoning permit | Permit status: Completed | Completion date: December 23, 2016 | Permit id: 739769 | |||||
SCORE 82 Interior demolition- for the interior demolition of non load-bearing partition walls and ceilings as per attached standard. Deviations from this standard will result in permit revocation and require submission of construction plans. Date: October 14, 2016 Contractor: App Philadelphia Construction Permit type: Demolition permit | Permit status: Completed | Completion date: December 28, 2016 | Permit id: 729448 | |||||
SCORE 82 Ez permit stadard alterations- for alterations to an existing one family dwelling as per attached standard. Deviations from this standard will result in permit revocation and require submission of construction plans. Date: October 31, 2016 Contractor: App Philadelphia Construction Permit type: Alteration permit | Permit status: Completed | Completion date: October 30, 2017 | Permit id: 733248 | |||||
SCORE 100 Rewire and installation 200amp service (sfd)east district Date: November 9, 2016 Contractor: Amptron Corp Permit type: Electrical permit | Permit status: Completed | Completion date: October 30, 2017 | Permit id: 735605 | |||||
For the demolition of an existing 1-story rear shed and paritial demoltion of 3rd story level and for the erection of a one story addition on the third floor level with a three story addition in the rear of the attached structure. Building for use as a single family dwelling. Building to be fully sprinklered. All work to be done per approved plans. If field conditions vary contact structural engineer prior to the start of any work. Separate permits required for all other work. Date: December 23, 2016 Permit type: Addition permit | Permit status: Completed | Completion date: November 3, 2017 | Permit id: 739770 | |||||
SCORE 100 Install one 90% furnace and air conditioning unit with duct work throughout. Date: April 4, 2017 Contractor: Amptron Corp Permit type: Mechanical permit | Permit status: Completed | Completion date: October 30, 2017 | Permit id: 772343 | |||||
SCORE 100 3 toilets,3 lavs,3 tubs and 1 ktichen sink (sfd)the installation shall comply with the philadelphia plumbing code, 2004 Date: April 7, 2017 Contractor: Just Plumbing And Heating Permit type: Plumbing permit | Permit status: Completed | Completion date: October 27, 2017 | Permit id: 773629 | |||||
For the amendment of previously approved permit# 7397 to removed fire suppression requirement. Building is not required to be sprinklered. Original permit approved for the demolition of an existing 1-story rear shed and paritial demoltion of 3rd story level and for the erection of a one story addition on the third floor level with a three story addition in the rear of the attached structure. Building for use as a single family dwelling. All work to be done per approved plans. If field conditions vary contact structural engineer prior to the start of any work. Separate permits required for all other work. Date: September 13, 2017 Permit type: Administrative permit | Permit status: Completed | Completion date: October 30, 2017 | Permit id: 794226 |