Suppression permit Date: September 23, 2013 Client: Sarah Development Llc | Permit status: Completed | Permit id: 487503 | |||||
Plumbing permit Date: May 26, 2010 Client: Sarah Development Llc | Permit status: Completed | Permit id: 281170 | |||||
New construction permit Date: May 20, 2013 Client: Sarah Development Llc | Permit status: Completed | Permit id: 467192 | |||||
Demolition permit Date: April 5, 2013 Client: Sarah Development Llc | Permit status: Completed | Permit id: 462535 | |||||
Electrical permit Date: September 5, 2013 Client: Sarah Development Llc | Permit status: Completed | Permit id: 493166 | |||||
Zoning/use permit Date: April 5, 2013 Client: Sarah Development Llc | Permit status: Completed | Permit id: 446549 | |||||
Plumbing permit Date: August 22, 2013 Client: Sarah Development Llc | Permit status: Completed | Permit id: 490848 | |||||
Mechanical permit Date: August 16, 2013 Client: Sarah Development Llc | Permit status: Completed | Permit id: 489639 | |||||
Permit for the complete demolition of all existing structures and for the erection of an attached structure maximum 35 feet high , for use as a two (2) family dwelling. (size and location as shown in the application). Date: March 5, 2013 Client: Sarah Development Llc | Applicant: Jih Zhen, Esquire | Permit type: Appeal | Permit status: Granted | Completion date: April 17, 2013 | Permit id: 20028 | |||||
Demolition permit Date: April 5, 2013 Client: Sarah Development Llc | Permit status: Completed | Permit id: 462535 | |||||
Mechanical permit Date: August 16, 2013 Client: Sarah Development Llc | Permit status: Completed | Permit id: 489639 | |||||
Plumbing permit Date: August 22, 2013 Client: Sarah Development Llc | Permit status: Completed | Permit id: 490848 | |||||
Plumbing permit Date: May 26, 2010 Client: Sarah Development Llc | Permit status: Completed | Permit id: 281170 | |||||
New construction permit Date: May 20, 2013 Client: Sarah Development Llc | Permit status: Completed | Permit id: 467192 | |||||
Zoning use permit Date: April 5, 2013 Client: Sarah Development Llc | Permit status: Completed | Permit id: 446549 | |||||
Electrical permit Date: September 5, 2013 Client: Sarah Development Llc | Permit status: Completed | Permit id: 493166 | |||||
Suppression permit Date: September 23, 2013 Client: Sarah Development Llc | Permit status: Completed | Permit id: 487503 | |||||
Permit for the complete demolition of all existing structures and for the erection of an attached structure maximum 35 feet high , for use as a two (2) family dwelling. (size and location as shown in the application). Date: March 5, 2013 Client: Sarah Development Llc | Applicant: Jih Zhen, Esquire | Permit type: Appeal | Permit status: Granted | Completion date: April 17, 2013 | Permit id: 20028 | |||||
SCORE 100 Installation of automatic sprinkler system in accordance with nfpa 13-r throughout three (3) story structure with two inch (2") fire service and backflow preventor per plans (two (2) dwelling units). Date: September 23, 2013 Contractor: Oneida Fire Protection Client: Sarah Development Llc | Permit type: Suppression permit | Permit status: Completed | Completion date: October 29, 2013 | Permit id: 487503 | |||||
SCORE 100 Installation of (2) 2-ton heat pumps (duplex) Date: August 16, 2013 Contractor: Anthony S. Rachuba Jr Client: Sarah Development Llc | Permit type: Mechanical permit | Permit status: Completed | Completion date: October 29, 2013 | Permit id: 489639 | |||||
SCORE 100 Install new 5" lateral, curb trap & fresh air inlet, 3 4" water service (sfd) pa20132330215 Date: August 22, 2013 Contractor: Drain Masters Plumbing Llc Client: Sarah Development Llc | Permit type: Plumbing permit | Permit status: Completed | Completion date: October 29, 2013 | Permit id: 490848 | |||||
SCORE 100 Plumbing permit Date: July 24, 2013 Contractor: Drain Masters Plumbing Llc Client: Sarah Development Llc | Permit status: Completed | Completion date: October 29, 2013 | Permit id: 485260 | |||||
SCORE 82 200amp service wiring throughout per 2008 nec (two family) Date: September 5, 2013 Contractor: Dg Electrical Contractors Client: Sarah Development Llc | Permit type: Electrical permit | Permit status: Completed | Completion date: January 3, 2014 | Permit id: 493166 | |||||
Complete demolition of existing structure in its entirety Date: April 5, 2013 Client: Sarah Development Llc | Permit type: Demolition permit | Permit status: Completed | Completion date: June 11, 2013 | Permit id: 462535 | |||||
SCORE 96 Erection of a three story structure with cellar 2nd and 3rd floor front bays for use as a duplex Date: May 20, 2013 Contractor: Msj Contractors Llc Client: Sarah Development Llc | Permit type: New construction permit | Permit status: Completed | Completion date: October 29, 2013 | Permit id: 467192 | |||||
SCORE 100 Replace 3 4" "k" water service Date: May 26, 2010 Contractor: Mr Ds Plumbing And Heating Client: Sarah Development Llc | Permit type: Plumbing permit | Permit status: Completed | Completion date: June 15, 2015 | Permit id: 281170 | |||||
SCORE 100 Replace stack and three fixtures Date: June 9, 2010 Contractor: Mr Ds Plumbing And Heating Client: Sarah Development Llc | Permit type: Plumbing permit | Permit status: Completed | Completion date: January 18, 2011 | Permit id: 283747 | |||||
Complete demo of existing structure in its entirety. Erection of a three story structure with cellar; 2nd and 3rd floor front bays for use as a duplex Date: April 5, 2013 Client: Sarah Development Llc | Permit type: Zoning/use permit | Permit status: Completed | Completion date: April 5, 2013 | Permit id: 446549 |