Suppression permit Date: November 22, 2010 Permit status: Completed | Permit id: 312977 | |||||
Fast form building permit Date: December 3, 2008 Permit status: Completed | Permit id: 191036 | |||||
Mechanical permit Date: January 8, 2014 Permit status: Completed | Permit id: 513562 | |||||
Demolition permit Date: August 21, 2013 Permit status: Completed | Permit id: 490568 | |||||
Plumbing permit Date: November 5, 2012 Permit status: Completed | Permit id: 434203 | |||||
Mechanical permit Date: February 8, 2013 Permit status: Completed | Permit id: 452623 | |||||
Mechanical permit Date: January 18, 2007 Permit status: Completed | Permit id: 50499 | |||||
Administrative permit Date: May 6, 2013 Permit status: Completed | Permit id: 469391 | |||||
Mechanical permit Date: June 8, 2012 Permit status: Completed | Permit id: 409792 | |||||
Plumbing permit Date: September 18, 2013 Permit status: Completed | Permit id: 489904 | |||||
Demolition permit Date: December 9, 2011 Permit status: Completed | Permit id: 377920 | |||||
Alteration permit Date: April 2, 2015 Permit status: Completed | Permit id: 597456 | |||||
Suppression permit Date: October 29, 2015 Permit status: Completed | Permit id: 648715 | |||||
Electrical permit Date: February 6, 2014 Permit status: Expired | Permit id: 514570 | |||||
Suppression permit Date: November 18, 2014 Permit status: Completed | Permit id: 574976 | |||||
Plumbing permit Date: December 9, 2010 Permit status: Completed | Permit id: 315327 | |||||
Fast form building permit Date: April 16, 2007 Permit status: Completed | Permit id: 69431 | |||||
Suppression permit Date: November 12, 2013 Permit status: Completed | Permit id: 505480 | |||||
Use permit Date: August 6, 2012 Permit status: Completed | Permit id: 418244 | |||||
Alteration permit Date: February 28, 2007 Permit status: Completed | Permit id: 56833 | |||||
Alteration permit Date: August 11, 2016 Permit status: Completed | Permit id: 706441 | |||||
Alteration permit Date: June 19, 2012 Permit status: Completed | Permit id: 410593 | |||||
Electrical permit Date: September 6, 2012 Permit status: Completed | Permit id: 425431 | |||||
Mechanical permit Date: February 6, 2015 Permit status: Completed | Permit id: 589106 | |||||
Mechanical permit Date: November 7, 2011 Permit status: Completed | Permit id: 371538 | |||||
Suppression permit Date: January 20, 2012 Permit status: Completed | Permit id: 383956 | |||||
Electrical permit Date: January 17, 2013 Permit status: Completed | Permit id: 441532 | |||||
Electrical permit Date: April 30, 2015 Permit status: Completed | Permit id: 597092 | |||||
Alteration permit Date: July 23, 2013 Permit status: Completed | Permit id: 482943 | |||||
Electrical permit Date: October 7, 2010 Permit status: Completed | Permit id: 298416 | |||||
Plumbing permit Date: March 5, 2007 Permit status: Completed | Permit id: 59362 | |||||
Electrical permit Date: March 26, 2007 Permit status: Completed | Permit id: 43309 | |||||
Plumbing permit Date: October 26, 2015 Permit status: Completed | Permit id: 647715 | |||||
Electrical permit Date: April 5, 2016 Permit status: Active | Permit id: 681840 | |||||
Alteration permit Date: July 19, 2010 Permit status: Completed | Permit id: 289977 | |||||
Demolition permit Date: September 26, 2014 Permit status: Completed | Permit id: 564377 | |||||
Demolition permit Date: January 12, 2012 Permit status: Completed | Permit id: 382933 | |||||
Alteration permit Date: August 22, 2011 Permit status: Completed | Permit id: 357673 | |||||
Electrical permit Date: August 8, 2011 Permit status: Expired | Permit id: 357165 | |||||
Plumbing permit Date: June 26, 2014 Permit status: Completed | Permit id: 545741 | |||||
Mechanical permit Date: November 8, 2010 Permit status: Completed | Permit id: 310427 | |||||
Suppression permit Date: January 19, 2011 Permit status: Completed | Permit id: 321300 | |||||
Demolition permit Date: July 8, 2016 Permit status: Active | Permit id: 705768 | |||||
Use permit Date: December 16, 2013 Permit status: Completed | Permit id: 509569 | |||||
Administrative permit Date: September 10, 2007 Permit status: Completed | Permit id: 101714 | |||||
Administrative permit Date: June 28, 2012 Permit status: Completed | Permit id: 413683 | |||||
Plumbing permit Date: August 15, 2011 Permit status: Completed | Permit id: 357820 | |||||
Alteration permit Date: June 13, 2014 Permit status: Completed | Permit id: 540817 | |||||
Alteration permit Date: March 3, 2009 Permit status: Expired | Permit id: 198196 | |||||
Suppression permit Date: September 6, 2016 Permit status: Active | Permit id: 719872 | |||||
Plumbing permit Date: September 23, 2016 Permit status: Completed | Permit id: 723964 | |||||
Mechanical permit Date: July 7, 2014 Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit status: Completed | Permit id: 547558 | |||||
Electrical permit Date: August 1, 2014 Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit status: Completed | Permit id: 551867 | |||||
Suppression permit Date: April 8, 2013 Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit status: Completed | Permit id: 463604 | |||||
Alteration permit Date: July 14, 2014 Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit status: Completed | Permit id: 547451 | |||||
Administrative permit Date: February 20, 2013 Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit status: Completed | Permit id: 454016 | |||||
Mechanical permit Date: October 3, 2013 Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit status: Completed | Permit id: 497010 | |||||
Plumbing permit Date: November 24, 2014 Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit status: Completed | Permit id: 575922 | |||||
Demolition permit Date: August 18, 2016 Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit status: Active | Permit id: 715934 | |||||
Alteration permit Date: September 3, 2013 Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit status: Completed | Permit id: 491385 | |||||
Administrative permit Date: February 12, 2014 Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit status: Completed | Permit id: 519436 | |||||
Electrical permit Date: March 18, 2013 Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit status: Completed | Permit id: 453463 | |||||
Electrical permit Date: March 11, 2015 Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit status: Completed | Permit id: 590125 | |||||
Mechanical permit Date: January 30, 2015 Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit status: Completed | Permit id: 585605 | |||||
Alteration permit Date: January 26, 2015 Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit status: Completed | Permit id: 584936 | |||||
Electrical permit Date: March 9, 2012 Permit status: Completed | Permit id: 388262 | |||||
Electrical permit Date: March 26, 2007 Permit status: Completed | Permit id: 43309 | |||||
Electrical permit Date: August 8, 2014 Permit status: Completed | Permit id: 548168 | |||||
Suppression permit Date: July 30, 2012 Permit status: Completed | Permit id: 419031 | |||||
Electrical permit Date: August 30, 2016 Permit status: Completed | Permit id: 716180 | |||||
Administrative permit Date: June 28, 2012 Permit status: Completed | Permit id: 413683 | |||||
Suppression permit Date: July 31, 2013 Permit status: Completed | Permit id: 486556 | |||||
Mechanical permit Date: November 7, 2011 Permit status: Completed | Permit id: 371538 | |||||
Demolition permit Date: December 9, 2011 Permit status: Completed | Permit id: 377920 | |||||
Suppression permit Date: April 20, 2015 Permit status: Completed | Permit id: 603026 | |||||
Demolition permit Date: May 1, 2013 Permit status: Completed | Permit id: 468401 | |||||
Electrical permit Date: October 16, 2015 Permit status: Completed | Permit id: 636123 | |||||
Plumbing permit Date: June 12, 2014 Permit status: Completed | Permit id: 542406 | |||||
Electrical permit Date: September 26, 2011 Permit status: Completed | Permit id: 359406 | |||||
Plumbing permit Date: February 14, 2012 Permit status: Completed | Permit id: 387902 | |||||
Plumbing permit Date: July 26, 2013 Permit status: Completed | Permit id: 485051 | |||||
Fast form building permit Date: March 29, 2007 Permit status: Completed | Permit id: 65337 | |||||
Mechanical permit Date: October 15, 2013 Permit status: Completed | Permit id: 500452 | |||||
Alteration permit Date: November 15, 2013 Permit status: Completed | Permit id: 505328 | |||||
Suppression permit Date: June 12, 2014 Permit status: Completed | Permit id: 542547 | |||||
Alteration permit Date: June 19, 2012 Permit status: Completed | Permit id: 410593 | |||||
Electrical permit Date: January 14, 2013 Permit status: Completed | Permit id: 447866 | |||||
Plumbing permit Date: June 29, 2015 Permit status: Completed | Permit id: 618510 | |||||
Administrative permit Date: September 10, 2007 Permit status: Completed | Permit id: 101714 | |||||
Alteration permit Date: March 26, 2007 Permit status: Completed | Permit id: 60961 | |||||
Mechanical permit Date: April 15, 2015 Permit status: Completed | Permit id: 602934 | |||||
Suppression permit Date: August 12, 2010 Permit status: Completed | Permit id: 295985 | |||||
Mechanical permit Date: October 19, 2012 Permit status: Completed | Permit id: 433646 | |||||
Demolition permit Date: September 26, 2014 Permit status: Completed | Permit id: 564377 | |||||
Plumbing permit Date: March 26, 2007 Permit status: Completed | Permit id: 64418 | |||||
Administrative permit Date: May 17, 2013 Permit status: Completed | Permit id: 462175 | |||||
Alteration permit Date: July 19, 2010 Permit status: Completed | Permit id: 289977 | |||||
Electrical permit Date: January 24, 2017 Permit status: Active | Permit id: 745448 | |||||
Mechanical permit Date: January 18, 2007 Permit status: Completed | Permit id: 50499 | |||||
Alteration permit Date: August 22, 2011 Permit status: Completed | Permit id: 357673 | |||||
Demolition permit Date: October 11, 2012 Permit status: Completed | Permit id: 432069 | |||||
Suppression permit Date: December 15, 2016 Permit status: Active | Permit id: 743995 | |||||
Alteration permit Date: September 29, 2016 Permit status: Active | Permit id: 723571 | |||||
Electrical permit Date: December 1, 2010 Permit status: Completed | Permit id: 306723 | |||||
Use permit Date: August 6, 2012 Permit status: Completed | Permit id: 418244 | |||||
Fast form building permit Date: June 24, 2008 Permit status: Completed | Permit id: 160436 | |||||
Mechanical permit Date: November 8, 2010 Permit status: Completed | Permit id: 310427 | |||||
Mechanical permit Date: January 8, 2014 Permit status: Completed | Permit id: 513562 | |||||
Alteration permit Date: March 3, 2009 Permit status: Expired | Permit id: 198196 | |||||
Use permit Date: December 16, 2013 Permit status: Completed | Permit id: 509569 | |||||
Suppression permit Date: August 16, 2011 Permit status: Completed | Permit id: 358485 | |||||
Plumbing permit Date: August 15, 2011 Permit status: Completed | Permit id: 357820 | |||||
Alteration permit Date: January 8, 2015 Permit status: Completed | Permit id: 581489 | |||||
Plumbing permit Date: September 23, 2016 Permit status: Completed | Permit id: 723964 | |||||
Mechanical permit Date: November 7, 2016 Permit status: Active | Permit id: 733416 | |||||
Demolition permit Date: July 8, 2016 Permit status: Expired | Permit id: 705768 | |||||
Alteration permit Date: June 13, 2014 Permit status: Completed | Permit id: 540817 | |||||
Plumbing permit Date: December 9, 2010 Permit status: Completed | Permit id: 315327 | |||||
SCORE 100 Replace existing sink fixture and add indirect waste for ice maker, "the installation will comply with the philadelphia plumbing code 2004" Date: November 24, 2014 Contractor: Lees Plumbing Inc Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit type: Plumbing permit | Permit status: Completed | Completion date: January 26, 2015 | Permit id: 575922 | |||||
SCORE 100 50-relocate exist lighting, 5-install exit lgts, 15-sw, 43-recept, 6-power to furniture system, 1-connect exhaust fan & existing pnl boards as per nec 2008 & nfpa 72 (comm office bldg) cc district Date: December 4, 2014 Contractor: Metro Electric Co Inc Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: April 23, 2015 | Permit id: 576040 | |||||
SCORE 100 For level ii interior alterations on partial 40th floor of an existing building. Alterations to include the demolition erection of partition walls, provide furnishings and finishes throughout as per approved plans. All work to be done per approved plans. If field conditions vary contact design professional prior to the start of any work. Separate permits required for mechanical, electrical, plumbing and fire supression work. Date: January 26, 2015 Contractor: Dlauro And Rodgers Inc Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: July 13, 2015 | Permit id: 584936 | |||||
SCORE 100 Alterations to existing hvac system in office space on 14th floor to include ductwork and vav boxes as per approved plans. Date: January 30, 2015 Contractor: Cms Mechanical Inc Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit type: Mechanical permit | Permit status: Completed | Completion date: April 7, 2015 | Permit id: 585605 | |||||
SCORE 100 No change in use and occupancy classification. Interior alterations as per approved plans. Separate permit required for mechanical, electrical, and plumbing work. Date: July 14, 2014 Contractor: Dlauro And Rodgers Inc Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: October 15, 2014 | Permit id: 547451 | |||||
SCORE 100 Interior alterations as per plans Date: February 6, 2013 Contractor: Dlauro And Rodgers Inc Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: January 31, 2014 | Permit id: 451015 | |||||
SCORE 100 Relocate 6 deffusers Date: January 9, 2013 Contractor: Lormar Mechanical Services Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit type: Mechanical permit | Permit status: Completed | Completion date: September 18, 2013 | Permit id: 447074 | |||||
SCORE 100 Furnish and install 8 cat 6 plenum cables and 6 cat 6 shielded plenum cables, longest run 1 as per 2008 nec (cc district) Date: March 11, 2014 Contractor: Gt Telecom Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: April 30, 2014 | Permit id: 523735 | |||||
SCORE 99 Rework 2 supply diffusers-office Date: July 7, 2014 Contractor: Oreland Sheet Metal Co Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit type: Mechanical permit | Permit status: Completed | Completion date: July 25, 2014 | Permit id: 547558 | |||||
SCORE 87 Tenant fit out, lighting, recepts, switches, interior alteration as per 2008 nec (cc district) for lf driscoll co llcadding 3 devices onto the fire alarm system as per nfpa72 Date: July 9, 2014 Contractor: Nesmith And Company Inc Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: November 24, 2014 | Permit id: 540839 | |||||
SCORE 100 Temporary certificate of occupancy Date: February 12, 2014 Contractor: Hunter Roberts Construction Gr Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit type: Administrative permit | Permit status: Completed | Completion date: February 21, 2014 | Permit id: 519436 | |||||
SCORE 100 Relocation of 78 existing sprinkler heads. Date: December 16, 2013 Contractor: Independence Fire Sprinkler Co Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit type: Suppression permit | Permit status: Completed | Completion date: August 12, 2014 | Permit id: 511460 | |||||
SCORE 100 Mechanical hvac alterations and installation of additional duct work, ceiling and linear diffusers, vav boxes, connect to existing system. Remaining portions of 33rd floor area as per plans and mechanical specifications Date: February 12, 2014 Contractor: Lormar Mechanical Services Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit type: Mechanical permit | Permit status: Completed | Completion date: May 21, 2015 | Permit id: 518745 | |||||
SCORE 100 Level 2 interior alterations to an existing office space on the 38th floor as per approved plans. Date: September 3, 2013 Contractor: Sullivan Company The Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: January 15, 2014 | Permit id: 491385 | |||||
SCORE 100 Hvac, including ductwork and mechanical equipment, as per plans. Date: August 7, 2013 Contractor: Lormar Mechanical Services Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit type: Mechanical permit | Permit status: Completed | Completion date: February 21, 2014 | Permit id: 486905 | |||||
SCORE 100 Interior alterations to 42nd floor as per plans. No change to building envelope. Separate permits required for electrical, plumbing, mechanical, and fire suppression. Date: November 4, 2014 Contractor: Bittenbender Construction Lp Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: December 17, 2015 | Permit id: 569280 | |||||
SCORE 100 Fire alarm system work, 2 existing speakers to retain, 2 relocated speaker strobes, 6 new speaker strobes connected to existing circuitry as per nfpa72 (cc district) Date: August 1, 2014 Contractor: Metro Electric Co Inc Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: October 15, 2014 | Permit id: 551867 | |||||
SCORE 100 Renovation existing space for new tenant install 90-lights, 15-light switch, 45-recepts, 2-furniture feed, 4-equipment feed & 7-fire alarm speaker strobe as per nec 2008 & nfpa 72 (comm) cc district Date: March 11, 2015 Contractor: New Light Electric Inc Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: May 5, 2015 | Permit id: 590125 | |||||
SCORE 98 Fit-out of fitness center and common corridors includes construction of shower and locker rooms, ceramic tile work and painting, new carpets, and ceilings. Work also inlcudes an isolated spring floor at the workout area. No work or changes to facade of building. Date: December 27, 2013 Contractor: Patriot Construction Inc Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: September 29, 2014 | Permit id: 508323 | |||||
SCORE 95 Furnish and install security equipment per 2008 nec (cc district)installation to comply with articles 300. 21 & 725 of the 2008 nec. Date: December 6, 2013 Contractor: Hatzel And Buehler Inc Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: April 14, 2014 | Permit id: 505173 | |||||
SCORE 100 For level ii alterations to an existing tenant space located on the 36th floor of an existing building. Alterations to include the demolition erection of parition walls, provide furnishings and finishes throughout. Building is fully sprinklered. All work to be done per approved plans. If field conditions vary contact design professional prior to the start of any work. Separate permits required for mechanical, electrical, plumbing and fire supression work. Date: November 4, 2014 Contractor: Bittenbender Construction Lp Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: February 2, 2015 | Permit id: 570572 | |||||
SCORE 100 Ez standard limited commercial alterations & repairs-change fixtures, flooring, wall finishes. For the limited demolition and commercial alterations as per attached standard. Deviations from this standard will result in permit revocation and require submission of construction plans. Date: May 2, 2017 Contractor: John Scarlett Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: June 17, 2017 | Permit id: 779747 | |||||
SCORE 100 Ez permit ductwork & warm-air appliances- for the installation of new ductwork, registers grilles diffusers, and warm-air appliances as per attached standard. Deviations from this standard will result in permit revocation and require submission of construction plans. Date: January 12, 2017 Contractor: Lormar Mechanical Services Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit type: Mechanical permit | Permit status: Completed | Completion date: April 17, 2017 | Permit id: 749514 | |||||
SCORE 100 Minor demo and construction of new partition walls to create offices. Date: January 29, 2013 Contractor: Sullivan Company The Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: April 30, 2013 | Permit id: 448912 | |||||
SCORE 100 Relocation of (6) sprinkler heads Date: July 29, 2013 Contractor: Independence Fire Sprinkler Co Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit type: Suppression permit | Permit status: Completed | Completion date: September 18, 2013 | Permit id: 485892 | |||||
SCORE 100 Relocation of existing 155 heads Date: April 8, 2013 Contractor: Independence Fire Sprinkler Co Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit type: Suppression permit | Permit status: Completed | Completion date: May 1, 2013 | Permit id: 463604 | |||||
SCORE 95 Install 22 speakers-strobes 1 nac panel 4 smoke detectors 1 heat detector 4 pull stations per 2008 & nfpa 72 nec (commercial) Date: March 18, 2013 Contractor: Hatzel And Buehler Inc Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: July 27, 2013 | Permit id: 453463 | |||||
SCORE 100 Relocating (15) sprinklers in suite 37 of heery international in the three logan building. Date: January 10, 2013 Contractor: Oliver Sprinkler Co Inc Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit type: Suppression permit | Permit status: Completed | Completion date: September 24, 2013 | Permit id: 447424 | |||||
SCORE 100 Relocate 6 difusers Date: July 23, 2013 Contractor: Lormar Mechanical Services Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit type: Mechanical permit | Permit status: Completed | Completion date: September 25, 2013 | Permit id: 484797 | |||||
SCORE 100 Relocate 3 diffusers Date: May 21, 2013 Contractor: Cms Mechanical Inc Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit type: Mechanical permit | Permit status: Completed | Completion date: January 15, 2014 | Permit id: 472688 | |||||
SCORE 100 Alterations: interior plumbing; 1st floor saxby coffee - the installation will comply with the philadlephia plumbing code 2004 Date: June 8, 2017 Contractor: Lormar Mechanical Services Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit type: Plumbing permit | Permit status: Completed | Completion date: July 6, 2017 | Permit id: 787833 | |||||
SCORE 100 Disconnect and reconnect front coffee wall counter for new counters. Replace 12 lighting fixtures as per 2008 nec. Date: May 15, 2017 Contractor: Vitale Philip J Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: June 14, 2017 | Permit id: 783618 | |||||
SCORE 98 Interior demolition of partition walls & level ii alterations to include new partition walls, glazing, upgrades to finishes. No structural work. All work shall be done in accordance with approved plans. Date: April 9, 2013 Contractor: Patriot Construction Inc Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: November 29, 2013 | Permit id: 462026 | |||||
SCORE 100 Hvac including ductwork and mechanical equipment as per plans. Date: October 3, 2013 Contractor: Lormar Mechanical Services Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit type: Mechanical permit | Permit status: Completed | Completion date: February 27, 2014 | Permit id: 497010 | |||||
SCORE 99 Relocate 2 diffusers. Date: April 17, 2013 Contractor: Oreland Sheet Metal Co Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit type: Mechanical permit | Permit status: Completed | Completion date: November 29, 2013 | Permit id: 465643 | |||||
SCORE 100 Interior selected partition demolition, new interior finishes, replaceent of selected interior items, expansion of the furness room and a new accessible family restroom - additional permits are required for electrical, plumbing, hvac and fire suppression Date: March 12, 2013 Contractor: A And E Construction Co Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: May 28, 2013 | Permit id: 456564 | |||||
SCORE 100 For level ii alterations to an existing tenant space located on the 37th floor of an existing building. Alterations to include the demolition erection of parition walls, provide furnishings and finishes throughout. Building is fully sprinklered. All work to be done per approved plans Date: October 27, 2017 Contractor: Dlauro And Rodgers Inc Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit type: Alteration permit | Permit status: Active | Completion date: November 20, 2017 | Permit id: 824102 | |||||
SCORE 100 Mechanical alteration, to include, installation of (2) cooling only, vav boxes with ductwork and controls. Relocate 34 diffusers. All work within existing tenant space. No penetration of fire rated assemblies. Less than 20 cfm Date: November 20, 2014 Contractor: Lormar Mechanical Services Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit type: Mechanical permit | Permit status: Completed | Completion date: April 8, 2015 | Permit id: 575459 | |||||
SCORE 100 Partial interior demolition of existing partitions and finishes throughout tenant space; installation of new partitions at conference room, reception, copy room and pantry per plans; new finishes throughout. Issuance of lawful occupancy sign. Separate permits required for all fire suppression, mechanical, electrical and plumbing work. Date: July 7, 2014 Contractor: Dlauro And Rodgers Inc Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: October 15, 2014 | Permit id: 545603 | |||||
SCORE 98 Interior alterations to include the erection of partition walls, doors, finishes and accessibility improvements. No structural work, no work to the facade of the building. Separate permits required for any mechanical, electrical, plumbing & fire suppression work. Date: June 20, 2014 Contractor: Patriot Construction Inc Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: July 25, 2014 | Permit id: 540066 | |||||
Interior alterations for a commercial office fit-out. Date: November 14, 2014 Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: April 2, 2015 | Permit id: 570801 | |||||
SCORE 100 Alterations to existing hvac stystem including ductwork as per approved plans. Date: July 9, 2014 Contractor: Lormar Mechanical Services Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit type: Mechanical permit | Permit status: Completed | Completion date: October 15, 2014 | Permit id: 545982 | |||||
SCORE 100 Remove and replace existing corridor lighting fixtures per 2008 nec (office building) Date: July 10, 2014 Contractor: Metro Electric Co Inc Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: October 21, 2014 | Permit id: 548476 | |||||
SCORE 100 Electrical work for tenant fit out per 2008 nec (office space) Date: July 25, 2014 Contractor: Metro Electric Co Inc Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: October 15, 2014 | Permit id: 548472 | |||||
SCORE 100 Level ii interior alterations to 49th floor of existing office building as per approved plans. Separate permits required for any mep & fire suppression work Date: May 14, 2014 Contractor: L F Driscoll Company Llc Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: August 12, 2014 | Permit id: 534489 | |||||
SCORE 100 Relocation of sprinkler heads. Date: April 5, 2013 Contractor: Independence Fire Sprinkler Co Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit type: Suppression permit | Permit status: Completed | Completion date: November 29, 2013 | Permit id: 463394 | |||||
SCORE 100 Amend permit no 448912 to reflect modified door swing from conference room and incorporate lawful occupancy sign for conference room. Date: February 20, 2013 Contractor: Sullivan Company The Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit type: Administrative permit | Permit status: Completed | Completion date: April 30, 2013 | Permit id: 454016 | |||||
SCORE 100 Demolition of acoustical ceilings, carpet, doors, frames, and non bearing walls-ez interior demolition- for the interior demolition of non load-bearing partition walls and ceilings as per attached standard. Deviations from this standard will result in permit revocation and require submission of construction plans. Date: August 18, 2016 Contractor: Bittenbender Construction Lp Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit type: Demolition permit | Permit status: Completed | Completion date: December 2, 2016 | Permit id: 715934 | |||||
SCORE 100 Installation of cat6 and rg6 coax low low voltage cable as per 2008 nec Date: December 15, 2010 Contractor: Charles H Macdonald Electric I Permit type: Electrical permit | Permit status: Completed | Completion date: March 14, 2011 | Permit id: 313423 | |||||
SCORE 100 Relocate 19 sprinklers on the 14th floor Date: January 20, 2015 Contractor: Oliver Sprinkler Co Inc Permit type: Suppression permit | Permit status: Completed | Completion date: April 7, 2015 | Permit id: 585310 | |||||
SCORE 100 F i 16 light fixtures, 2 dimmers, 1 switch, 7 occ sensors, 8 floor boxes, 3 gfcis, 24 receptacles, 2 quads, relocate lighting & fire alarm equipment. Date: February 5, 2015 Contractor: Shoreline Electric Inc Permit type: Electrical permit | Permit status: Completed | Completion date: May 28, 2015 | Permit id: 586412 | |||||
SCORE 100 Relocate (23) existing sprinkler heads in ordr to accommodate new wall and ceiling layout. Date: February 19, 2013 Contractor: A And S Sprinkler Co Inc Permit type: Suppression permit | Permit status: Completed | Completion date: September 24, 2013 | Permit id: 454263 | |||||
SCORE 100 Relocate 27 diffusers Date: February 8, 2013 Contractor: Lormar Mechanical Services Permit type: Mechanical permit | Permit status: Completed | Completion date: September 24, 2013 | Permit id: 452623 | |||||
SCORE 100 Install 3 cat 6 data cables - 1 rg-6 coax cables - install coppreend fiber tie cable from 42nd floor to telco room - install 61 speakers and cabling - as per 2008 nec Date: March 8, 2013 Contractor: Bluestone Communications Inc Permit type: Electrical permit | Permit status: Completed | Completion date: July 31, 2017 | Permit id: 452969 | |||||
SCORE 100 Relocate 137 heads in commcast complex Date: October 11, 2013 Contractor: Independence Fire Sprinkler Co Permit type: Suppression permit | Permit status: Completed | Completion date: January 2, 2014 | Permit id: 499696 | |||||
SCORE 100 Relocate 7 sprinklers in the 14th floor Date: July 17, 2014 Contractor: Oliver Sprinkler Co Inc Permit type: Suppression permit | Permit status: Completed | Completion date: October 15, 2014 | Permit id: 549884 | |||||
SCORE 100 For partial demolition of interior non-bearing partitions and for the replacement of the ceiling in an existing office space (high-rise, level ii alterations). Alterations also include new non-bearing partitions to create new room configurations. Separate permits required for electrical, mechanical, plumbing and fire suppression systems. Date: December 19, 2013 Contractor: Sullivan Company The Permit type: Alteration permit | Permit status: Completed | Completion date: April 22, 2014 | Permit id: 510860 | |||||
SCORE 95 Install fa speaker strobe 2 heat dets and 2 smokes in accordance with nfpa-72(commercial)(cc dist) Date: January 17, 2013 Contractor: Hatzel And Buehler Inc Permit type: Electrical permit | Permit status: Completed | Completion date: April 27, 2013 | Permit id: 441532 | |||||
SCORE 100 Interior demolition of non load bearing walls and ceiling only. No demolition to fire rated assembiles. No other work allowed under this permit. Contact streets department for dumpster permit and footway closure. Date: November 21, 2012 Contractor: Sullivan Company The Permit type: Demolition permit | Permit status: Completed | Completion date: May 28, 2013 | Permit id: 439300 | |||||
SCORE 100 Installation of kitchen sink Date: June 12, 2014 Contractor: Lees Plumbing Inc Permit type: Plumbing permit | Permit status: Completed | Completion date: August 4, 2014 | Permit id: 542406 | |||||
SCORE 100 Install voice data cabling to 3 locations, copper fiber backbone from 42nd floor to 26 37 floors & av coax from 26 to 27 floors. Installation to comply with articles 300. 21, 720, 725, 7 & 8 of the 2008 nec. Date: November 8, 2013 Contractor: Bluestone Communications Inc Permit type: Electrical permit | Permit status: Completed | Completion date: April 23, 2014 | Permit id: 497101 | |||||
SCORE 100 Relocate lighting, install new recpt, new switches, wire & connect furniture systems & all wiring connected to existing panelboards as per nec 2008 (comm) Date: February 21, 2013 Contractor: Metro Electric Co Inc Permit type: Electrical permit | Permit status: Completed | Completion date: April 27, 2013 | Permit id: 450693 | |||||
SCORE 100 Disconnect & reconnect existing appliances and hvac equipment disconnect & reconnect existing (20)2x4 light per 2008 nec (commercial) Date: January 14, 2013 Contractor: Donald A Pusey Inc Permit type: Electrical permit | Permit status: Completed | Completion date: July 20, 2013 | Permit id: 447866 | |||||
SCORE 100 Relocate diffusers Date: January 7, 2013 Contractor: Lormar Mechanical Services Permit type: Mechanical permit | Permit status: Completed | Completion date: September 24, 2013 | Permit id: 446516 | |||||
SCORE 100 Relocate 3 exit lights,36 downlights,8 switches,2 track lights,8 duplex recepts,5 existing f a devices as per 2008 nec and nfpa72(multi story office) Date: January 4, 2013 Contractor: Metro Electric Co Inc Permit type: Electrical permit | Permit status: Completed | Completion date: March 7, 2013 | Permit id: 446395 | |||||
SCORE 100 Interior alterations as per plans. All work to be in accordance with approved plans. Date: November 19, 2012 Contractor: Dlauro And Rodgers Inc Permit type: Alteration permit | Permit status: Completed | Completion date: February 11, 2013 | Permit id: 438030 | |||||
SCORE 100 Relocate (31) existing sprinkler heads in order to accommodate tenant wall and ceiling layout as per all nfpa no 13 and local codes. (33rd floor) Date: January 28, 2014 Contractor: A And S Sprinkler Co Inc Permit type: Suppression permit | Permit status: Completed | Completion date: August 4, 2014 | Permit id: 516966 | |||||
SCORE 100 Relocate (17) existing sprinkler heads in order to accommodate tenant wall and ceiling layout as per all nfpa no 13 and local codes. (37th floor) Date: January 28, 2014 Contractor: A And S Sprinkler Co Inc Permit type: Suppression permit | Permit status: Completed | Completion date: August 4, 2014 | Permit id: 516968 | |||||
SCORE 100 Relocate existing sprinkler heads (commercial) Date: September 6, 2016 Contractor: A And S Sprinkler Co Inc Permit type: Suppression permit | Permit status: Completed | Completion date: March 20, 2017 | Permit id: 719872 | |||||
SCORE 99 Rework hvac to conform to new layout Date: May 1, 2007 Contractor: Oreland Sheet Metal Co Permit type: Mechanical permit | Permit status: Completed | Completion date: July 30, 2007 | Permit id: 71068 | |||||
SCORE 100 Provide & install 264 amp catergory 6 pleum 4-pair & 528 commscope rg-6 quad shield plenum coax longest cable run 284 as per nec 2008 cc district Date: October 16, 2015 Contractor: Bluestone Communications Inc Permit type: Electrical permit | Permit status: Completed | Completion date: November 17, 2015 | Permit id: 636123 | |||||
SCORE 86 Install 39 new lts, 1 exit sign, 12 sws, 25 recepts and 4 furniture feeds (cc dist) Date: September 28, 2007 Contractor: Klf Electric Permit type: Electrical permit | Permit status: Completed | Completion date: January 11, 2008 | Permit id: 106002 | |||||
SCORE 100 Amend permit # 97852 to reflect change of contractor Date: September 10, 2007 Contractor: Dlauro And Rodgers Inc Permit type: Administrative permit | Permit status: Completed | Completion date: March 6, 2008 | Permit id: 101714 | |||||
SCORE 100 Interior alterations to reconfigure office space to include: new doors,flooring, work stations, millwork including ada compliant sink and pantry. Date: August 22, 2011 Contractor: Dlauro And Rodgers Inc Permit type: Alteration permit | Permit status: Completed | Completion date: November 8, 2011 | Permit id: 357673 | |||||
SCORE 100 Furnish and install (1)sink - connect to existing services Date: August 15, 2011 Contractor: Lormar Mechanical Services Permit type: Plumbing permit | Permit status: Completed | Completion date: November 8, 2011 | Permit id: 357820 | |||||
SCORE 95 Furnish and install lighting and power throughout space as per 2008 nec (cc dist) Date: January 4, 2011 Contractor: Hatzel And Buehler Inc Permit type: Electrical permit | Permit status: Completed | Completion date: April 20, 2011 | Permit id: 313829 | |||||
SCORE 100 Install 2 pantry sinks and 2 floor drains in pantry(commercial-high rise) Date: August 27, 2012 Contractor: Lees Plumbing Inc Permit type: Plumbing permit | Permit status: Completed | Completion date: December 14, 2012 | Permit id: 423965 | |||||
SCORE 95 Install lighting, lighting control, furniture feeds, wiring devices, & tele data back boxes throughout space per 2008 nec (commercial) Date: September 26, 2012 Contractor: Hatzel And Buehler Inc Permit type: Electrical permit | Permit status: Completed | Completion date: December 12, 2012 | Permit id: 424294 | |||||
SCORE 95 Demo existing lights and recepts, furnish and install new fixtures, recepts, and associated branch wire. Install new 225 amp bus plug, new 100kva ups module and 2 new panels, no fire alarm work included (cc district) Date: June 14, 2007 Contractor: Hatzel And Buehler Inc Permit type: Electrical permit | Permit status: Completed | Completion date: November 26, 2007 | Permit id: 76543 | |||||
SCORE 100 Relocate (56) sprinkler heads. Date: October 8, 2014 Contractor: A And S Sprinkler Co Inc Permit type: Suppression permit | Permit status: Completed | Completion date: August 26, 2015 | Permit id: 566808 | |||||
Renovations of general office space on the 40th fl. Of the bell atlantic tower bldg. Interior renovations only. Date: February 28, 2007 Permit type: Alteration permit | Permit status: Completed | Completion date: September 24, 2007 | Permit id: 56833 | |||||
SCORE 98 Tenant fit-out 38th floor Date: February 22, 2007 Contractor: Patriot Construction Inc Permit type: Alteration permit | Permit status: Completed | Completion date: July 30, 2007 | Permit id: 57010 | |||||
SCORE 95 Relocate (46) 2x4s,18 duplex receptacles and 8 furniture feeds per 2008 nec (office space) Date: November 3, 2014 Contractor: Hatzel And Buehler Inc Permit type: Electrical permit | Permit status: Completed | Completion date: May 5, 2015 | Permit id: 571724 | |||||
SCORE 100 For the installation of an hvac system to include ductwork and mechanical equipment as per plans (36th floor, unit b). System to include forty (40) registers diffusers. Per approved plans. Separate permit required for electrical, plumbing, fire suppression. Date: November 14, 2014 Contractor: Lormar Mechanical Services Permit type: Mechanical permit | Permit status: Completed | Completion date: January 30, 2015 | Permit id: 572216 | |||||
SCORE 100 Relocate 36 existing sprinkler heads (commercial) Date: November 6, 2014 Contractor: A And S Sprinkler Co Inc Permit type: Suppression permit | Permit status: Completed | Completion date: February 2, 2015 | Permit id: 572360 | |||||
SCORE 95 Furnish and install all necessary lighting,power and equipment,58 lighting fixtures,8 floor outlets,28 duplex receptacles,new 120 20v panel,new 45kva transformer,9 occupancy sensors and 5 new exit signs per 2008 nec (office space) Date: December 5, 2014 Contractor: Hatzel And Buehler Inc Permit type: Electrical permit | Permit status: Completed | Completion date: May 28, 2015 | Permit id: 572913 | |||||
SCORE 100 Replace liminaires provide new lighting controls provide power to new modular furniture partitions per 2008 nec code(central dist)e-1 thru e-15 fa1 fa2 fa3 Date: October 7, 2010 Contractor: Stephen Vasoli Permit type: Electrical permit | Permit status: Completed | Completion date: August 10, 2012 | Permit id: 298416 | |||||
SCORE 100 Interior alterations per plan 3rd floor Date: October 20, 2010 Contractor: Frank R Lamarra Builders And Con Permit type: Alteration permit | Permit status: Completed | Completion date: December 20, 2010 | Permit id: 305307 | |||||
SCORE 100 Level ii alteartions includes build out two corridor walls on 6th floor. Certificate of occupancy required for tenant spaces Date: September 16, 2015 Contractor: L F Driscoll Company Llc Permit type: Alteration permit | Permit status: Completed | Completion date: February 24, 2016 | Permit id: 634974 | |||||
SCORE 98 Interior renovations as per plan. Date: February 1, 2007 Contractor: Patriot Construction Inc Permit type: Alteration permit | Permit status: Completed | Completion date: April 3, 2007 | Permit id: 52091 | |||||
SCORE 100 Fast form building permit Date: January 29, 2007 Contractor: A And S Sprinkler Co Inc Permit status: Completed | Completion date: April 18, 2007 | Permit id: 53123 | |||||
SCORE 93 Communications systems: 8 locations consisting of 1 cat5e cable Date: January 31, 2007 Contractor: Richard Manopello Jr Permit type: Electrical permit | Permit status: Completed | Completion date: February 10, 2009 | Permit id: 53725 | |||||
SCORE 100 Remove and replace (20) registers diffuser Date: February 1, 2007 Contractor: Cms Mechanical Inc Permit type: Mechanical permit | Permit status: Completed | Completion date: April 3, 2007 | Permit id: 53903 | |||||
SCORE 100 F&i 34 category 5e plenum cables in the new suite average cable pull 125 feet per 2008 nec (office space)installation to comply with articles 300. 21, 300. 22 & 8 of the 2008 nec. Date: July 16, 2014 Contractor: Belles Electrical Contractors Permit type: Electrical permit | Permit status: Expired | Completion date: July 16, 2014 | Permit id: 539764 | |||||
SCORE 95 25 new 2x4 fixtures, 14 new 2x2, 4 new pendants, new down lgihts, add 32 new duplex recepts, 2 gfi recepts, re-use all existing wiring from demolition Date: March 26, 2007 Contractor: Hatzel And Buehler Inc Permit type: Electrical permit | Permit status: Completed | Completion date: August 13, 2007 | Permit id: 55277 | |||||
SCORE 95 Install fire alarm system per plans. Date: October 6, 2014 Contractor: Hatzel And Buehler Inc Permit type: Electrical permit | Permit status: Completed | Completion date: November 21, 2015 | Permit id: 558125 | |||||
SCORE 95 Relocate 5-pendant & fixtures & install 3-new pendant fixtures as per nec 2008 (office bldg) Date: September 11, 2014 Contractor: Hatzel And Buehler Inc Permit type: Electrical permit | Permit status: Completed | Completion date: January 9, 2016 | Permit id: 561071 | |||||
SCORE 91 Install (41) cat 5c plenum cables - longest run 125 Date: February 13, 2007 Contractor: George White Jr Permit type: Electrical permit | Permit status: Expired | Completion date: April 3, 2007 | Permit id: 56140 | |||||
SCORE 100 17,0 square feet, interior demolition of non load bearing walls and ceilings only. No other work allowed under this permit. Separate permits required for renovation. No structural changes. Must maintain all code required fire rating on wall and floor ceiling assemblies. Call inspector prior for initial inspection prior to the start of work. Date: September 26, 2014 Contractor: Bittenbender Construction Lp Permit type: Demolition permit | Permit status: Completed | Completion date: November 18, 2014 | Permit id: 564377 | |||||
SCORE 99 For mechanical demolition of exist. Ductwork & removal of exist. Ceiling variable air volume (vav) boxes for the installation of one (1) ceiling mounted air conditioning unit for computer rm, (139) grilles registers diffusers (grds), vav boxes for tie-in to exist. Supply ductwork, & all associated supply return exhaust ductwork within an existing high-rise office building. Date: March 19, 2013 Contractor: Oreland Sheet Metal Co Permit type: Mechanical permit | Permit status: Completed | Completion date: April 30, 2013 | Permit id: 450789 | |||||
SCORE 95 Install new lighting, receptacles, furniture feeds, occupancy sensors, poke thru & back boxes for tele data & av throughout per 2008 nec (commercial) Date: February 25, 2013 Contractor: Hatzel And Buehler Inc Permit type: Electrical permit | Permit status: Completed | Completion date: July 27, 2013 | Permit id: 450796 | |||||
SCORE 100 Installation of pantry sink with electric water heater. Date: February 4, 2013 Contractor: Lees Plumbing Inc Permit type: Plumbing permit | Permit status: Completed | Completion date: August 12, 2013 | Permit id: 451359 | |||||
SCORE 95 Remove device for new ceiling tile & replace device in same location with no addl wiring or new devices as per nfpa 72 cc district Date: September 2, 2015 Contractor: Hatzel And Buehler Inc Permit type: Electrical permit | Permit status: Completed | Completion date: November 4, 2015 | Permit id: 636300 | |||||
SCORE 100 Provide & install 490amp category 6 plenum 4-pair & 508 commscope rg-6 quad shield plenum coax longest cable run is 295 feet as per nec 2008 Date: October 16, 2015 Contractor: Bluestone Communications Inc Permit type: Electrical permit | Permit status: Completed | Completion date: November 17, 2015 | Permit id: 636612 | |||||
SCORE 100 Level ii interior alterations (no change of occupancy) to first floor office space in an existing high rise office building as per approved plans. Existing building fully sprinklered. Separate permits required for any mep or fire suppression work Date: October 1, 2015 Contractor: L F Driscoll Company Llc Permit type: Alteration permit | Permit status: Completed | Completion date: February 24, 2016 | Permit id: 639929 | |||||
SCORE 100 Install (34) ceiling mounted speker strobe, (9) wall mounted speaker strobe, (4) wall mount strobe, (4) smoke detector as per drawings as per nfpa-72. Date: February 16, 2017 Contractor: New Light Electric Inc Permit type: Electrical permit | Permit status: Completed | Completion date: March 13, 2017 | Permit id: 751147 | |||||
SCORE 95 Furnish 5 fire alarm relay devices and 3 signing devices. Reuse exisiting panels as per nfpa 72 cc district Date: March 17, 2017 Contractor: Hatzel And Buehler Inc Permit type: Electrical permit | Permit status: Completed | Completion date: April 24, 2017 | Permit id: 756526 | |||||
SCORE 100 Demo of existing branch ligting circs and install temp lts for future tenant fir outs as per 2008 nec(commercial high rise)(cc dist) Date: February 2, 2012 Contractor: Charles H Macdonald Electric I Permit type: Electrical permit | Permit status: Expired | Completion date: February 2, 2012 | Permit id: 386174 | |||||
SCORE 95 Install 5 strobes and 4 speaker strobes as per nfpa-72(commercial)(cc dist) Date: March 8, 2012 Contractor: Hatzel And Buehler Inc Permit type: Electrical permit | Permit status: Completed | Completion date: May 31, 2012 | Permit id: 386597 | |||||
SCORE 100 Replacement only of kitchen sink Date: February 14, 2012 Contractor: Lees Plumbing Inc Permit type: Plumbing permit | Permit status: Completed | Completion date: September 12, 2012 | Permit id: 387902 | |||||
SCORE 100 Install cat5e and rg6 coax low voltage cable as per 2008 nec. Longest run 220(commercial-high rise)(cc dist) Date: March 9, 2012 Contractor: Charles H Macdonald Electric I Permit type: Electrical permit | Permit status: Completed | Completion date: April 9, 2014 | Permit id: 388262 | |||||
SCORE 100 Relocate 821 sprinkler heads on floors 16-22 Date: October 26, 2011 Contractor: A And S Sprinkler Co Inc Permit type: Suppression permit | Permit status: Completed | Completion date: July 11, 2012 | Permit id: 370757 | |||||
SCORE 100 Furnish and install 18 sinks, 4 wc, 3 lavs, 17 urinals with new piping. Furnish and install 49 wc, and 42 lavs with out new piping (floors 16-22 only) Date: November 3, 2011 Contractor: Lormar Mechanical Services Permit type: Plumbing permit | Permit status: Completed | Completion date: July 11, 2012 | Permit id: 370800 | |||||
SCORE 95 Office space-furnish & install all lighting,power & security system per plans attached per 2008 nec (cc district) Date: December 15, 2011 Contractor: Hatzel And Buehler Inc Permit type: Electrical permit | Permit status: Completed | Completion date: July 20, 2012 | Permit id: 370937 | |||||
SCORE 100 Hvac, including mechanical units and ductworkd, as per plans for office Date: November 7, 2011 Contractor: Lormar Mechanical Services Permit type: Mechanical permit | Permit status: Completed | Completion date: July 11, 2012 | Permit id: 371538 | |||||
SCORE 100 Corporate offices-install 11 locations consisting of a 2 cat6 plenum cables. Cat6 cabling will be installed in j hooks, all sleeves and penetrations will be fire stopped as per 2008 nec articles 300. 21 & 800. Date: January 11, 2012 Contractor: Lanconnect Inc Permit type: Electrical permit | Permit status: Completed | Completion date: September 27, 2014 | Permit id: 372397 | |||||
SCORE 100 Furnish and install fire alarm per 2008 nec & nfpa 72 (office space) Date: October 29, 2013 Contractor: Shoreline Electric Inc Permit type: Electrical permit | Permit status: Completed | Completion date: January 3, 2014 | Permit id: 497327 | |||||
SCORE 95 Furnish and install new lighting and power throughout space per 2008 nec. Provide 60a max mcb in relocated panel apl27b. Date: October 31, 2013 Contractor: Hatzel And Buehler Inc Permit type: Electrical permit | Permit status: Completed | Completion date: November 21, 2015 | Permit id: 497872 | |||||
SCORE 100 Install 3-sinks for coffee stations 2 on 26th floor & 1 on the 27th floor install 3 water heaters above sinks (office) Date: October 7, 2013 Contractor: E J Raith Mechanical Inc Permit type: Plumbing permit | Permit status: Completed | Completion date: January 2, 2014 | Permit id: 499176 | |||||
SCORE 100 Relocation of 1 heads in comcast complex Date: October 11, 2013 Contractor: Independence Fire Sprinkler Co Permit type: Suppression permit | Permit status: Completed | Completion date: February 27, 2014 | Permit id: 499693 | |||||
SCORE 100 Demo for interior non bearing wall partitions only. Additional permits required for alterations. Date: December 9, 2011 Contractor: Sullivan Company The Permit type: Demolition permit | Permit status: Completed | Completion date: January 13, 2012 | Permit id: 377920 | |||||
SCORE 95 Remove & relocate (34) 2x4 fxts. Add (10) new down lts, (8) new wall washers, (36) new dupl recepts. (6) new dedicated dupl recepts. Re-use all circuitry from demolition. (cc dist) Date: April 27, 2007 Contractor: Hatzel And Buehler Inc Permit type: Electrical permit | Permit status: Completed | Completion date: August 13, 2007 | Permit id: 65352 | |||||
SCORE 100 Repalce 41 existig 2x2 light fixtures 41 2x2 led light fixtures in the same location. Replace 11 existing lights with 11 led lights in same location with no additional wiring as per 2008 nec (cc district) Date: April 5, 2016 Contractor: Metro Electric Co Inc Permit type: Electrical permit | Permit status: Expired | Completion date: April 5, 2016 | Permit id: 681840 | |||||
SCORE 100 Install new lightig, switching, power and electrical service, no tele comm work included, existing fire alarm devices to remain (center city district) Date: April 26, 2007 Contractor: Mcgoldrick Electric Inc Permit type: Electrical permit | Permit status: Completed | Completion date: November 21, 2015 | Permit id: 70090 | |||||
SCORE 96 Furnish and install 34 voice and 34 data cables cat5e plenum rated ( cc dist) Date: April 20, 2007 Contractor: James Carrigan Inc Permit type: Electrical permit | Permit status: Expired | Completion date: April 20, 2007 | Permit id: 70315 | |||||
SCORE 100 Interior demolition, to comply with ez permit standards-ez interior demolition- for the interior demolition of non load-bearing partition walls and ceilings as per attached standard. Deviations from this standard will result in permit revocation and require submission of construction plans. Date: July 8, 2016 Contractor: Dlauro And Rodgers Inc Permit type: Demolition permit | Permit status: Completed | Completion date: May 22, 2017 | Permit id: 705768 | |||||
SCORE 92 (o) sk (1) fx Date: January 24, 2007 Contractor: Thomas Marcinek Permit type: Plumbing permit | Permit status: Completed | Completion date: February 9, 2007 | Permit id: 51906 | |||||
SCORE 100 Relocate (12) diffusers Date: October 1, 2007 Contractor: Lormar Mechanical Services Permit type: Mechanical permit | Permit status: Completed | Completion date: March 6, 2008 | Permit id: 106315 | |||||
SCORE 92 Finish and install (1) kitchen sink and connect to existing services Date: October 10, 2007 Contractor: Thomas Marcinek Permit type: Plumbing permit | Permit status: Completed | Completion date: December 10, 2007 | Permit id: 108347 | |||||
SCORE 91 Install (20-30) category 5e plenum cables, longest run 75 (cc dist) Date: October 15, 2007 Contractor: George White Jr Permit type: Electrical permit | Permit status: Expired | Completion date: October 15, 2007 | Permit id: 109063 | |||||
SCORE 100 Fast form building permit Date: June 24, 2008 Contractor: A And S Sprinkler Co Inc Permit status: Completed | Completion date: May 1, 2009 | Permit id: 160436 | |||||
SCORE 100 Interior non-load bearing demolition and removal of debris (38th floor - sw corner) Date: July 16, 2013 Contractor: Cippco Contracting Inc Permit type: Demolition permit | Permit status: Completed | Completion date: March 12, 2014 | Permit id: 483354 | |||||
SCORE 100 Installation of a pantry sink Date: July 26, 2013 Contractor: Lormar Mechanical Services Permit type: Plumbing permit | Permit status: Completed | Completion date: September 25, 2013 | Permit id: 484866 | |||||
SCORE 95 Furnish and install lighting & power throughout per 2008 nec (office space) Date: August 30, 2013 Contractor: Hatzel And Buehler Inc Permit type: Electrical permit | Permit status: Completed | Completion date: April 14, 2014 | Permit id: 485749 | |||||
SCORE 100 Relocate (840) existing sprinkler heads in order to accommodate new tenant layout as per all nfpa no. 13 and local codes (floors 28 through 33) Date: July 31, 2013 Contractor: A And S Sprinkler Co Inc Permit type: Suppression permit | Permit status: Completed | Completion date: February 21, 2014 | Permit id: 486556 | |||||
SCORE 100 Furnish & install 58-category 6 cables-plenum, furnish & install 44- rg6 plenum coaxial cables, longest run as per nec 2008 (office bldg) Date: October 7, 2013 Contractor: Gt Telecom Permit type: Electrical permit | Permit status: Completed | Completion date: April 30, 2014 | Permit id: 489652 | |||||
SCORE 100 Install 100-lighting fixtures, 23-switches, 65-recept, 1-connect to existing circuitry as per nec 2008 ( office bldg) Date: August 9, 2012 Contractor: Metro Electric Co Inc Permit type: Electrical permit | Permit status: Completed | Completion date: October 3, 2012 | Permit id: 420221 | |||||
SCORE 100 Furnish and install 1 wc, 1 shower, 1 lav, 1 sink(high rise office) Date: August 9, 2012 Contractor: Lormar Mechanical Services Permit type: Plumbing permit | Permit status: Completed | Completion date: October 2, 2012 | Permit id: 420856 | |||||
SCORE 100 Replace bathroom fixtures and add kitchen sinks and assoicated piping (office space) Date: September 18, 2013 Contractor: E J Raith Mechanical Inc Permit type: Plumbing permit | Permit status: Completed | Completion date: March 28, 2014 | Permit id: 489904 | |||||
SCORE 95 Remove & relocate 6 2x4 light fixtures, 1 2x2 light fixtures, 2 gfi receptacles, 2 wall furniture feeds, 3 duplex recepts as per 2008 nec (office space) no additional wiring and no other work to be done on this permit Date: August 21, 2013 Contractor: Hatzel And Buehler Inc Permit type: Electrical permit | Permit status: Completed | Completion date: November 6, 2013 | Permit id: 490449 | |||||
SCORE 100 Interior wall demolition of dry walls at office s, ceilings and flooring. No bearing walls to be demolished. Date: August 21, 2013 Contractor: Sullivan Company The Permit type: Demolition permit | Permit status: Completed | Completion date: October 15, 2013 | Permit id: 490568 | |||||
SCORE 100 Installation of voice,data and fiber optic cabling per 2008 nec (office space) Date: October 2, 2013 Contractor: M Gitlin Co Inc Permit type: Electrical permit | Permit status: Expired | Completion date: October 2, 2013 | Permit id: 491477 | |||||
SCORE 100 Installation of a pantry sink Date: September 11, 2013 Contractor: Lees Plumbing Inc Permit type: Plumbing permit | Permit status: Completed | Completion date: September 25, 2013 | Permit id: 493304 | |||||
SCORE 100 Relocating (28) sprinklers in the ryan llc space in suite 3829 at three logan square Date: September 9, 2013 Contractor: Oliver Sprinkler Co Inc Permit type: Suppression permit | Permit status: Completed | Completion date: November 29, 2013 | Permit id: 493496 | |||||
SCORE 95 Furnish and install fire alarm equipment per 2008 nec & nfpa 72 (office space) Date: October 15, 2013 Contractor: Hatzel And Buehler Inc Permit type: Electrical permit | Permit status: Completed | Completion date: April 14, 2014 | Permit id: 493825 | |||||
SCORE 100 Furnish and install 37 2x4 lights,(1) 2x2, 15 downlights and 15 switches per 2008 nec (office space) Date: September 19, 2013 Contractor: Shoreline Electric Inc Permit type: Electrical permit | Permit status: Completed | Completion date: November 6, 2013 | Permit id: 493989 | |||||
SCORE 100 Interior alterations 26th & 27th floors, including new partitions, structural modifications for partitions, ceilings, accessibility upgrades, upgrades to finishes, new furnishings, fixtures, doors frames hardware, additional permits req: electrical, plumbing, mechanical,sprinklers. Existing high rise co on record, no change in use - occupancy classification. Date: September 27, 2013 Contractor: Sullivan Company The Permit type: Alteration permit | Permit status: Completed | Completion date: January 2, 2014 | Permit id: 495411 | |||||
SCORE 100 Intsallation of new double interlock pre-action system in 43rd floor lab server room in accordance with nfpa 13. Separate permit required for any electrical work. Date: March 6, 2014 Contractor: A And S Sprinkler Co Inc Permit type: Suppression permit | Permit status: Completed | Completion date: April 22, 2014 | Permit id: 517418 | |||||
SCORE 100 Installation of one sink, connect to existing service Date: June 19, 2012 Contractor: Lormar Mechanical Services Permit type: Plumbing permit | Permit status: Completed | Completion date: September 4, 2012 | Permit id: 411489 | |||||
SCORE 100 Power-re use existing service, devices and circuits lighting-relocate existing lighting as needed to realize new layout all lighting to be controlled by occupancy sensors per 2008 nec, fire alarm as per plans. Date: July 27, 2012 Contractor: Current Electrical Solutions Permit type: Electrical permit | Permit status: Expired | Completion date: July 27, 2012 | Permit id: 413061 | |||||
SCORE 100 Tco in conjunction with a p# 366012. Floors 16-22 Date: June 28, 2012 Contractor: Hunter Roberts Construction Gr Permit type: Administrative permit | Permit status: Completed | Completion date: June 28, 2012 | Permit id: 413683 | |||||
SCORE 100 Interior alterations: partial 40th floor - spring creek investment management offices Date: July 17, 2012 Contractor: Dlauro And Rodgers Inc Permit type: Alteration permit | Permit status: Completed | Completion date: October 2, 2012 | Permit id: 416076 | |||||
SCORE 100 Install cat6 plenum cables for voice and data as per 2008 nec(commercial office space)(cc dist) Date: August 15, 2012 Contractor: Bluestone Communications Inc Permit type: Electrical permit | Permit status: Completed | Completion date: May 25, 2016 | Permit id: 416983 | |||||
SCORE 98 Interior fit-out to office building. Date: August 13, 2012 Contractor: Patriot Construction Inc Permit type: Alteration permit | Permit status: Completed | Completion date: December 14, 2012 | Permit id: 418318 | |||||
SCORE 100 Relocate existing sprinkler heads in order to accommodate new tenant fit-out as per all nfpa no. 13 and local codes. Date: July 30, 2012 Contractor: A And S Sprinkler Co Inc Permit type: Suppression permit | Permit status: Completed | Completion date: October 2, 2012 | Permit id: 419031 | |||||
SCORE 100 Relocate 6 sprinkler heads. Date: July 31, 2012 Contractor: A And S Sprinkler Co Inc Permit type: Suppression permit | Permit status: Completed | Completion date: September 17, 2012 | Permit id: 419486 | |||||
SCORE 100 Remove existing 2 ton water cooled heat pump. Install new 3 ton water cooled heat pump with ductwork. Date: August 2, 2012 Contractor: Lormar Mechanical Services Permit type: Mechanical permit | Permit status: Completed | Completion date: September 4, 2012 | Permit id: 419838 | |||||
SCORE 100 Provide and install cat 6 plenum cables @ 125 average. Provide and install cat 5e plenum cables @ 125 average. All cabling will be installed in j-hooks per code as per 2008 nec(cc district) Date: December 11, 2015 Contractor: Lanconnect Inc Permit type: Electrical permit | Permit status: Expired | Completion date: December 11, 2015 | Permit id: 651531 | |||||
SCORE 100 (o) wc sh lav sk (4)fx Date: March 29, 2007 Contractor: Lees Plumbing Inc Permit type: Plumbing permit | Permit status: Completed | Completion date: September 27, 2007 | Permit id: 65307 | |||||
SCORE 95 Remove and reinstall 8-2x2,3 pendants, duplex recepts as per 2008 nec Date: June 8, 2012 Contractor: Hatzel And Buehler Inc Permit type: Electrical permit | Permit status: Completed | Completion date: August 8, 2012 | Permit id: 409967 | |||||
SCORE 100 Relocate 76 sprinkler heads - 7th floor Date: June 12, 2012 Contractor: A And S Sprinkler Co Inc Permit type: Suppression permit | Permit status: Completed | Completion date: October 2, 2012 | Permit id: 410478 | |||||
SCORE 100 Interior alterations as per plans. Date: June 19, 2012 Contractor: Dlauro And Rodgers Inc Permit type: Alteration permit | Permit status: Completed | Completion date: September 4, 2012 | Permit id: 410593 | |||||
SCORE 100 Audio visual per 2008 nec. Installation to comply with articles 300. 21, 725 & 800. Date: July 12, 2012 Contractor: M Gitlin Co Inc Permit type: Electrical permit | Permit status: Expired | Completion date: July 12, 2012 | Permit id: 411118 | |||||
SCORE 100 Relocate 19 diffusers Date: June 15, 2012 Contractor: Lormar Mechanical Services Permit type: Mechanical permit | Permit status: Completed | Completion date: September 4, 2012 | Permit id: 411240 | |||||
SCORE 95 Install 4 pull stations, 25 speaker strobes, 19 strobes, 4 detectors and 2 booster panels as per nfpa72 (cc district) Date: January 24, 2014 Contractor: Hatzel And Buehler Inc Permit type: Electrical permit | Permit status: Completed | Completion date: September 6, 2014 | Permit id: 511264 | |||||
SCORE 95 Install new lighting and power throughout fire alarm install 8 speaker-strobes,1 smoke detectors and relocate 7 speaker strobes per 2008 nec & nfpa (office space) Date: January 24, 2014 Contractor: Hatzel And Buehler Inc Permit type: Electrical permit | Permit status: Completed | Completion date: May 2, 2014 | Permit id: 512096 | |||||
SCORE 95 Tennant fit out Date: September 6, 2007 Contractor: Cyma Builders And Const Mgmt Inc Permit type: Alteration permit | Permit status: Completed | Completion date: March 6, 2008 | Permit id: 97852 | |||||
SCORE 100 Relocate (20) existing sprinkler heads - 34th floor Date: November 28, 2012 Contractor: A And S Sprinkler Co Inc Permit type: Suppression permit | Permit status: Completed | Completion date: January 24, 2013 | Permit id: 440064 | |||||
SCORE 100 8-relocate lighting 8-switches 11-receptacles 3-box & string for voice data wires per 2008 nec (office space) Date: November 20, 2012 Contractor: Metro Electric Co Inc Permit type: Electrical permit | Permit status: Completed | Completion date: January 29, 2013 | Permit id: 438926 | |||||
SCORE 95 Add (20) new 2x4s and (36) downlights, add (56) new duplex recepts, 3- dedicated duplex recepts, re-use all existing circuitry, remove and relocate (6) fire alarm devices and add 4- new fire alarm devices, add (25) voice data cables with terminations. Date: March 26, 2007 Contractor: Hatzel And Buehler Inc Permit type: Electrical permit | Permit status: Completed | Completion date: August 13, 2007 | Permit id: 43309 | |||||
SCORE 100 Remove and replace 5 ton water soursce heat pump with duct work, relocate 4 diffusers within tenant space no penetration of fire rated assemblies Date: October 19, 2012 Contractor: Lormar Mechanical Services Permit type: Mechanical permit | Permit status: Completed | Completion date: March 4, 2013 | Permit id: 433646 | |||||
SCORE 100 Install locations consisting of 2 cat6 plenum cables. All cabling will be installd in j hooks. All penetrations will be firestopped. Longest run is 125ft. All work done in accordance with 2008 nec(high rise-commercial bldg)(cc dist) Date: November 2, 2012 Contractor: Lanconnect Inc Permit type: Electrical permit | Permit status: Completed | Completion date: August 3, 2013 | Permit id: 434149 | |||||
SCORE 100 44th floor - interior alterations (plumbing) - replace the existing (7)water closets - install one new pantry sink with associate waste, water supply piping and apurtenances Date: November 5, 2012 Contractor: Lees Plumbing Inc Permit type: Plumbing permit | Permit status: Completed | Completion date: November 8, 2015 | Permit id: 434203 | |||||
SCORE 100 Fixture for coffee shop 1-3 compartment sink, 1-hand sink, 3 indirect waste or dishwasher, ice machine and pitcher rinse sink (commercial) Date: October 15, 2012 Contractor: Lees Plumbing Inc Permit type: Plumbing permit | Permit status: Completed | Completion date: March 4, 2013 | Permit id: 432602 | |||||
SCORE 100 Issuance of lawful occupancy sign for existing assembly space (conference, training & lunch room) in the 10th floor of an existing structure (office building). No alterations are authorized by this permit. Date: May 17, 2013 Contractor: Structure Tone,Inc Permit type: Administrative permit | Permit status: Completed | Completion date: August 6, 2013 | Permit id: 462175 | |||||
SCORE 79 Installing 2 new showers, 2 lavs, 1 ks, 1 indirect waste for ice machine. Date: May 30, 2007 Contractor: Kacprowicz Kenneth Permit type: Plumbing permit | Permit status: Completed | Completion date: July 7, 2008 | Permit id: 79418 | |||||
SCORE 100 Install (489) plenum category 6e data cables and (11) rg6 coax cables to (1) server room in customer suite. Extend (2) 25 pair category 5e cables from customer server room, the 15th floor telecom riser closet. Typical j-hook supports in ceilings. Longest horizontal run is approximately 250. (cc dist). Date: July 17, 2007 Contractor: New Line Communications Inc Permit type: Electrical permit | Permit status: Completed | Completion date: November 8, 2007 | Permit id: 79943 | |||||
SCORE 100 Relocation of looby shop, fitout for same. Date: June 28, 2012 Contractor: Hunter Roberts Construction Gr Permit type: Alteration permit | Permit status: Completed | Completion date: September 17, 2012 | Permit id: 409136 | |||||
SCORE 99 Hvac renovation to entire floor as per plans Date: June 1, 2007 Contractor: Oreland Sheet Metal Co Permit type: Mechanical permit | Permit status: Completed | Completion date: September 17, 2007 | Permit id: 77913 | |||||
SCORE 100 Minor electrical alterations in an existing building as per 2008 nec. Date: June 20, 2017 Contractor: Vitale Philip J Permit type: Electrical permit | Permit status: Completed | Completion date: September 27, 2017 | Permit id: 793455 | |||||
SCORE 100 Relocate 16 existing sprinkler heads in order to accommodate tenant fitout as per all nfpa no. 13 and local codes. Date: May 14, 2013 Contractor: A And S Sprinkler Co Inc Permit type: Suppression permit | Permit status: Completed | Completion date: August 10, 2013 | Permit id: 471239 | |||||
SCORE 100 Add new devices and relocate 2 devices Date: January 19, 2007 Contractor: Shoreline Electric Inc Permit type: Electrical permit | Permit status: Completed | Completion date: July 13, 2007 | Permit id: 47533 | |||||
SCORE 99 Modify existing hvac system to accomodate new tenant floor layout. Activity is on the 40th floor, barish rosenthal space. Date: January 17, 2007 Contractor: Oreland Sheet Metal Co Permit type: Mechanical permit | Permit status: Completed | Completion date: February 7, 2007 | Permit id: 47905 | |||||
SCORE 100 Interior fitout of floor corporate offices on floors 28 thru 32 and partial 33 Date: August 9, 2013 Contractor: Hunter Roberts Construction Gr Permit type: Alteration permit | Permit status: Completed | Completion date: March 19, 2014 | Permit id: 480023 | |||||
SCORE 95 Install 5 duplex & 5 quad receptacles, 6 occupancy sensors, 1 exhaust fan, 1 hot water heater feed & relocate 2x4 light fixtures. Date: May 14, 2012 Contractor: Hatzel And Buehler Inc Permit type: Electrical permit | Permit status: Completed | Completion date: September 25, 2012 | Permit id: 404794 | |||||
SCORE 100 Relocate 16 sprinkler heads Date: May 15, 2012 Contractor: Independence Fire Sprinkler Co Permit type: Suppression permit | Permit status: Completed | Completion date: November 28, 2012 | Permit id: 405101 | |||||
SCORE 100 Installation of restroom: water coset, lavatory, point of service water heater Date: May 29, 2012 Contractor: Lees Plumbing Inc Permit type: Plumbing permit | Permit status: Completed | Completion date: December 14, 2012 | Permit id: 406947 | |||||
SCORE 100 Furnish and install cat 5e plenum cables. Longest run is 125" as per 2008 nec(commercial office)(cc dist) Date: June 29, 2012 Contractor: Gt Telecom Permit type: Electrical permit | Permit status: Completed | Completion date: July 10, 2012 | Permit id: 408415 | |||||
SCORE 100 Minor demolition of millwork and non bearing walls Date: May 1, 2013 Contractor: Sullivan Company The Permit type: Demolition permit | Permit status: Completed | Completion date: May 28, 2013 | Permit id: 468401 | |||||
SCORE 100 Interior fit out, upgrades to finishes, millwork, office furnishings, partitions, fixtures, as indicated per submitted plans. Additional permits req: electrical,plumbing, hvac, sprinklers. No change in use or occupancy classification, co for record only. Date: May 10, 2013 Contractor: Sullivan Company The Permit type: Alteration permit | Permit status: Completed | Completion date: August 1, 2013 | Permit id: 468980 | |||||
SCORE 100 Amend original permit #366012 to include co for 2oth floor. The original permit indicated co for floors 16 thru 22, but inadvertantly omiitted the 20th floor. No constrcuition under this permit. All construction included under original permit. Date: May 6, 2013 Contractor: Hunter Roberts Construction Gr Permit type: Administrative permit | Permit status: Completed | Completion date: May 8, 2013 | Permit id: 469391 | |||||
SCORE 95 Remove & reinstall 6 2x4, 1 downlight, duplex receptacles only as per 2008 nec (office space) no other work to be done on this permit Date: April 16, 2013 Contractor: Hatzel And Buehler Inc Permit type: Electrical permit | Permit status: Completed | Completion date: July 27, 2013 | Permit id: 465546 | |||||
SCORE 100 Installation of pantry sink Date: April 11, 2013 Contractor: Lees Plumbing Inc Permit type: Plumbing permit | Permit status: Completed | Completion date: August 10, 2013 | Permit id: 464379 | |||||
SCORE 100 Modify branch power add-relocate receptacles. Replace luminaires. Date: April 10, 2013 Contractor: Stephen Vasoli Permit type: Electrical permit | Permit status: Completed | Completion date: August 3, 2013 | Permit id: 462958 | |||||
SCORE 99 Install ductwork and relocate diffuser as per plan. New diffusers. Date: April 4, 2013 Contractor: Mccloskey Mechanical Cont Inc Permit type: Mechanical permit | Permit status: Completed | Completion date: February 6, 2014 | Permit id: 461367 | |||||
SCORE 100 Installation of water closet, lavatory and drinking fountain Date: March 19, 2013 Contractor: John Uebele Jr Permit type: Plumbing permit | Permit status: Completed | Completion date: May 29, 2013 | Permit id: 459757 | |||||
SCORE 100 Level ii additional interior office fit-out of the balance of 33rd floor. Date: January 15, 2014 Contractor: Hunter Roberts Construction Gr Permit type: Alteration permit | Permit status: Completed | Completion date: March 19, 2014 | Permit id: 504527 | |||||
SCORE 100 Level ii alterations as per plan. Date: November 15, 2013 Contractor: Dlauro And Rodgers Inc Permit type: Alteration permit | Permit status: Completed | Completion date: July 24, 2014 | Permit id: 505328 | |||||
SCORE 100 Relocate (23) existing sprinkler heads in order to accommodate tenant wall and ceiling layout as per all nfpa no. 13 and local codes. Date: November 12, 2013 Contractor: A And S Sprinkler Co Inc Permit type: Suppression permit | Permit status: Completed | Completion date: June 30, 2014 | Permit id: 505480 | |||||
SCORE 88 Install 54 category 5e plenum cables to 24 wall locations (longest run is 150) per 2008 nec (office bldg) Date: November 8, 2013 Contractor: Vincent Nejman Permit type: Electrical permit | Permit status: Expired | Completion date: November 8, 2013 | Permit id: 500922 | |||||
SCORE 99 Replace exisiting diffusers with new Date: October 15, 2013 Contractor: Oreland Sheet Metal Co Permit type: Mechanical permit | Permit status: Completed | Completion date: January 15, 2014 | Permit id: 500452 | |||||
SCORE 100 Interior alterations as per plan. Date: January 24, 2007 Contractor: Dlauro And Rodgers Inc Permit type: Alteration permit | Permit status: Completed | Completion date: April 18, 2007 | Permit id: 50070 | |||||
SCORE 100 Tenant fit out electrical fire alarm per 2008 nec & nfpa 72 (office space) Date: December 2, 2013 Contractor: Charles H Macdonald Electric I Permit type: Electrical permit | Permit status: Completed | Completion date: April 14, 2014 | Permit id: 500911 | |||||
SCORE 95 Install 4 new speaker storbes and relocate 2 existing speaker storbes per 2008 nec & npfa 72(office space) Date: August 8, 2014 Contractor: Hatzel And Buehler Inc Permit type: Electrical permit | Permit status: Completed | Completion date: September 6, 2014 | Permit id: 548168 | |||||
SCORE 100 Relocate 34 sprinklers on 14th floor berkadia and corridor space at three logan square. Date: July 10, 2014 Contractor: Oliver Sprinkler Co Inc Permit type: Suppression permit | Permit status: Expired | Completion date: August 18, 2014 | Permit id: 548477 | |||||
SCORE 100 (o) sk sh (2) fx Date: February 5, 2007 Contractor: Lees Plumbing Inc Permit type: Plumbing permit | Permit status: Completed | Completion date: September 4, 2007 | Permit id: 54559 | |||||
SCORE 100 Install 1-sink & water heater install new drain line & water (office) Date: June 26, 2014 Contractor: Joseph Rosati Permit type: Plumbing permit | Permit status: Completed | Completion date: October 15, 2014 | Permit id: 545741 | |||||
SCORE 100 Furnish & install 71-cat 5e plenum cables average cable 1 as per nec 2008 cc district installation to comply with articles 300. 21, 300. 22 & 8 of the 2008 nec. Date: September 16, 2014 Contractor: Belles Electrical Contractors Permit type: Electrical permit | Permit status: Completed | Completion date: March 15, 2017 | Permit id: 546456 | |||||
SCORE 100 Relocating 41 sprinklers on the 49th floor office area of three logan. Date: June 3, 2014 Contractor: Oliver Sprinkler Co Inc Permit type: Suppression permit | Permit status: Completed | Completion date: May 21, 2015 | Permit id: 540341 | |||||
SCORE 100 Build out two conferance rooms and three office and open space office environment on 1st flootr. As temp office for construction of new comcast tower. Date: June 13, 2014 Contractor: L F Driscoll Company Llc Permit type: Alteration permit | Permit status: Completed | Completion date: August 12, 2014 | Permit id: 540817 | |||||
SCORE 100 Install kitchen sink and associated piping Date: June 18, 2014 Contractor: Tracey Mechanical Inc Permit type: Plumbing permit | Permit status: Completed | Completion date: July 8, 2014 | Permit id: 542131 | |||||
SCORE 100 Interior alterations ,upgrades to finishes, millwork, furnishings, for existing office space. No change in use-occupancy classification. Additional permits req: electrical, plumbing, hvac, sprinklers. Date: August 29, 2012 Contractor: Dlauro And Rodgers Inc Permit type: Alteration permit | Permit status: Completed | Completion date: January 24, 2013 | Permit id: 423676 | |||||
SCORE 100 Installation of hvac system including vav boxes, ductwork, registers and diffusers per plans (office space). Separate permits required for any electrical or plumbing work. Date: September 27, 2012 Contractor: Cms Mechanical Inc Permit type: Mechanical permit | Permit status: Completed | Completion date: January 16, 2013 | Permit id: 423670 | |||||
SCORE 100 Relocate (4) sprinkler heads on 36th floor Date: August 20, 2012 Contractor: A And S Sprinkler Co Inc Permit type: Suppression permit | Permit status: Completed | Completion date: March 18, 2013 | Permit id: 422982 | |||||
SCORE 100 Install 2-cat5 e plenum cable to 50-loc exist voice data rack in room 1335, term exist patch panel, inst & term 40-wall jack & 10-office furn jacks as per nec 2008 articles 300. 21 & 800. Date: March 22, 2013 Contractor: Bolef Silas Permit type: Electrical permit | Permit status: Expired | Completion date: March 22, 2013 | Permit id: 455255 | |||||
SCORE 100 Furnish and install 1-15kva transformer, 2 panels, lights, motion sensors and recepts, Date: January 19, 2007 Contractor: Shoreline Electric Inc Permit type: Electrical permit | Permit status: Completed | Completion date: July 13, 2007 | Permit id: 45555 | |||||
SCORE 89 Furnish and install voice data outlets cat5e plenum rated, 28 cubicals, 11 offices 39 drops, longest run 150 Date: January 24, 2007 Contractor: Crystal Ball Contracting Inc Permit type: Electrical permit | Permit status: Completed | Completion date: July 14, 2010 | Permit id: 45651 | |||||
SCORE 86 Install new lights, 25 switches, recepts, 8 exit signs, reuse existing service, with no expected change in load Date: February 22, 2007 Contractor: Klf Electric Permit type: Electrical permit | Permit status: Expired | Completion date: February 22, 2007 | Permit id: 50614 | |||||
SCORE 100 Add one kitche sink to the 40th flor coffee station Date: November 15, 2013 Contractor: E J Raith Mechanical Inc Permit type: Plumbing permit | Permit status: Completed | Completion date: June 30, 2014 | Permit id: 506217 | |||||
SCORE 100 Relocate 24 supply openings connected to existing vavs and duct work. Install (1) water source heat pump for server room. Relocate existing thermometer Date: November 18, 2013 Contractor: Elliott Lewis Corporation Permit type: Mechanical permit | Permit status: Completed | Completion date: July 8, 2014 | Permit id: 506513 | |||||
SCORE 100 Interior alterations to offce tenant space partial 37th floor per plans Date: January 7, 2013 Contractor: Dlauro And Rodgers Inc Permit type: Alteration permit | Permit status: Completed | Completion date: October 25, 2013 | Permit id: 445846 | |||||
SCORE 100 Alterations to existing hvac system to include ductwork and mechanical equipment as per approved plans. Date: January 8, 2014 Contractor: Lormar Mechanical Services Permit type: Mechanical permit | Permit status: Completed | Completion date: April 22, 2014 | Permit id: 513562 | |||||
SCORE 100 Install 1 light fixtures 5 receptacles 2-400amp,480v feeders,1-200amp 480v feeder 4-112. 5 kva intergratd power centers,2-125amp liebert ac units maintain existing fire alarm and install new preaction system for data room per 2008 nec & npfa 72(office bldg) see log Date: February 6, 2014 Contractor: Wm Aj Shaeffers Sons Inc Permit type: Electrical permit | Permit status: Expired | Completion date: February 6, 2014 | Permit id: 514570 | |||||
SCORE 95 Furnish and install lighting & power throughout additional 33rd floor space per 2008 nec (office space) Date: February 10, 2014 Contractor: Hatzel And Buehler Inc Permit type: Electrical permit | Permit status: Completed | Completion date: April 30, 2014 | Permit id: 516580 | |||||
SCORE 100 Remove and relocate lay-in fixtures. Replace existing 2x4 lay-in fixture with new 2x4 lay-in fixture. Install 15 new occupancy sensors. Install 6 new exit signs. Install new power for offices and open area all fed from existing circuiting per 2008 nec (office bldg) Date: December 26, 2013 Contractor: Mirarchi Brothers Inc Permit type: Electrical permit | Permit status: Expired | Completion date: December 26, 2013 | Permit id: 507995 | |||||
SCORE 100 Install 106 cat6 plenum cables 75 average. Cables to be installed in j-hooks per article 8 firestopped per article 300. 21 of the 2008 nec. Date: December 4, 2013 Contractor: Lanconnect Inc Permit type: Electrical permit | Permit status: Completed | Completion date: April 14, 2014 | Permit id: 509433 | |||||
SCORE 100 49th floor - replace plumbing fixtures in an existing toilet room - (7)water closets and (4)lavatories Date: December 12, 2013 Contractor: Lees Plumbing Inc Permit type: Plumbing permit | Permit status: Completed | Completion date: May 21, 2015 | Permit id: 510056 | |||||
SCORE 100 49th floor (office fitness center) - (6)stall showers, (2)water closets, (6)lavatories, (4)floor drains and a washing machine drain Date: December 12, 2013 Contractor: Lees Plumbing Inc Permit type: Plumbing permit | Permit status: Completed | Completion date: September 29, 2014 | Permit id: 510057 | |||||
SCORE 100 Minor demo, construction of 2 offices, nonbearing walls, minimal millwork modifications, carpet and paint as per sealed submitted plan. Fire rated assemblies are required to be maintained at all times. Plumbing, electrical, mechanical, and fire suppression work require additional permits. Call the inspector prior to starting work. Date: November 8, 2012 Contractor: Sullivan Company The Permit type: Alteration permit | Permit status: Completed | Completion date: January 24, 2013 | Permit id: 435565 | |||||
SCORE 100 Relocation of 9 sprinklers on the 3rd floor of three logan coffee Date: November 8, 2012 Contractor: Oliver Sprinkler Co Inc Permit type: Suppression permit | Permit status: Completed | Completion date: March 4, 2013 | Permit id: 436901 | |||||
SCORE 95 Install duplex recepts, 6 poke thrus, 1 bus plug switch, 1 kva transformer, 1 120 208v 100amp panel, 1 enclosed circuit breaker, tele data back-boxes, 1 meter, re-lamp fixtures as needed throughout space as per 2008 nec(office space) Date: December 4, 2012 Contractor: Hatzel And Buehler Inc Permit type: Electrical permit | Permit status: Completed | Completion date: January 8, 2013 | Permit id: 437497 | |||||
SCORE 98 For demo. Of exit. Partition walls & for prescriptive alterations w. No change of occupancy classification within an exit. High-rise mixed-use office building to include erection of partitions for open private office, conference room, & kitchenette spaces; work areas to be fully sprinklered. Date: July 23, 2013 Contractor: Patriot Construction Inc Permit type: Alteration permit | Permit status: Completed | Completion date: November 1, 2013 | Permit id: 482943 | |||||
SCORE 100 Interior alterations to existing office space as per plans. Date: February 16, 2012 Contractor: Sullivan Company The Permit type: Alteration permit | Permit status: Completed | Completion date: April 11, 2012 | Permit id: 387287 | |||||
SCORE 100 Install 5 lt fix, 4 lt sw, 5 rec. Reuse existing circs from demo as per 2008 nec. No change in load(commercial)(cc dist) Date: March 1, 2012 Contractor: New Light Electric Inc Permit type: Electrical permit | Permit status: Completed | Completion date: June 12, 2012 | Permit id: 390917 | |||||
SCORE 100 Tenant fit out, alterations, upgrades to finishes. No change in use-occupancy classification. Addl permits req: electrical, plumbing, hvac, sprinklers Date: March 21, 2012 Contractor: Sullivan Company The Permit type: Alteration permit | Permit status: Completed | Completion date: July 31, 2012 | Permit id: 392762 | |||||
SCORE 100 Tenant fit out for office as per plan. Date: March 29, 2012 Contractor: Structure Tone,Inc Permit type: Alteration permit | Permit status: Completed | Completion date: July 31, 2012 | Permit id: 393076 | |||||
SCORE 100 Tenant fit-out - new lighting devides - lighting control system - ups - panelboards and associated branch circuiting - as per 2008 nec Date: June 22, 2012 Contractor: Charles H Macdonald Electric I Permit type: Electrical permit | Permit status: Completed | Completion date: September 18, 2012 | Permit id: 393405 | |||||
SCORE 95 Alterations of an existing tenant space on the 15th floor of an existing high rise building. The entire floor is a single tenant. All work shall conform to the approved plans. Date: May 22, 2007 Contractor: Cyma Builders And Const Mgmt Inc Permit type: Alteration permit | Permit status: Completed | Completion date: September 17, 2007 | Permit id: 73060 | |||||
SCORE 100 Remove 4 existing fa devices for new ceiling installation. Reinstall existing devices in exact location fin new finishes. Recertify system per 2008 nec (restaurant)cc district Date: September 22, 2016 Contractor: Metro Electric Co Inc Permit type: Electrical permit | Permit status: Completed | Completion date: September 30, 2016 | Permit id: 723976 | |||||
SCORE 100 No change in use and occupancy classification. Level ii interior alterations as per approved plans. Separate permit required for any mep and fire suppression work. Date: September 29, 2016 Contractor: Haas Peters Construction Group Permit type: Alteration permit | Permit status: Completed | Completion date: March 20, 2017 | Permit id: 723571 | |||||
SCORE 100 Remove and replace sink and faucet in pantry. Connect to existing plumbing- no modifications Date: September 23, 2016 Contractor: Bofinger And Breslin Permit type: Plumbing permit | Permit status: Completed | Completion date: October 13, 2016 | Permit id: 723964 | |||||
SCORE 100 Install 32-led downlights, 2- pendant fixtures, 2-gfci recepts, 5-duplex recepts as per nec 2008 cc district Date: August 30, 2016 Contractor: Metro Electric Co Inc Permit type: Electrical permit | Permit status: Completed | Completion date: September 30, 2016 | Permit id: 716180 | |||||
SCORE 100 For level ii alterations to an existing space for use as a take out restaurant, alterations to include the erection of partition walls, provide accessibility improvements, finishes and furnishings throughout. Building is fully sprinklered. All work to be done per approved plans. If field conditions vary contact design professional prior to the start of any work. Separate permits required for mechanical, electrical, plumbing and fire suppression work. Date: August 11, 2016 Contractor: Dlauro And Rodgers Inc Permit type: Alteration permit | Permit status: Completed | Completion date: September 30, 2016 | Permit id: 706441 | |||||
SCORE 100 Interior fit out of floors 16 thru 22 for office use in an existing office building.. Date: January 24, 2012 Contractor: Hunter Roberts Construction Gr Permit type: Alteration permit | Permit status: Completed | Completion date: July 18, 2012 | Permit id: 366012 | |||||
SCORE 100 Relocate (19) diffusers Date: August 12, 2011 Contractor: Lormar Mechanical Services Permit type: Mechanical permit | Permit status: Completed | Completion date: November 8, 2011 | Permit id: 357920 | |||||
SCORE 100 Relocation of (15) sprinkler heads Date: August 16, 2011 Contractor: Oliver Sprinkler Co Inc Permit type: Suppression permit | Permit status: Completed | Completion date: November 8, 2011 | Permit id: 358485 | |||||
SCORE 100 Installation of new lighting,switches & recepts as per plans. Instal fire alarm devices as per plans Date: September 26, 2011 Contractor: Current Electrical Solutions Permit type: Electrical permit | Permit status: Completed | Completion date: November 30, 2011 | Permit id: 359406 | |||||
SCORE 100 Install 22 locations consisting of (2) cat 6 plenum cables, all cabling will be installed in "j" hooks per 2008 nec, all penetrations will be fire stopped as per 2008 nec (cc dist) Date: September 16, 2011 Contractor: Lanconnect Inc Permit type: Electrical permit | Permit status: Completed | Completion date: April 30, 2014 | Permit id: 361461 | |||||
SCORE 98 Interior demolition of non bearing partitions and ceilings throughout floor 16 thru 21 Date: July 22, 2011 Contractor: Delta Bjds Inc Permit type: Demolition permit | Permit status: Completed | Completion date: February 22, 2012 | Permit id: 354412 | |||||
SCORE 98 Interior demo of ceiling tile and floor carpet tile and soft dem of closet shelving for office. Date: July 26, 2011 Contractor: Delta Bjds Inc Permit type: Demolition permit | Permit status: Completed | Completion date: February 22, 2012 | Permit id: 354879 | |||||
SCORE 100 Safe off electric on floors 16, 17 18, 19, 20, 21, & 22 for demolition by others, install 8 temporary lights on each floor utilizing existing emergency lighting circuits as per 2008 nec (cc district) Date: August 8, 2011 Contractor: Liberty Integrated Solutions Permit type: Electrical permit | Permit status: Expired | Completion date: August 12, 2011 | Permit id: 357165 | |||||
SCORE 100 Office fit out of 5 floors. Plumbing to incl installation of 9 sinks in panty(commercial-office) Date: April 19, 2012 Contractor: Bofinger And Breslin Permit type: Plumbing permit | Permit status: Completed | Completion date: July 31, 2012 | Permit id: 394484 | |||||
SCORE 99 Furnish and install hvac, duct devices and supplemental units, piping, accessory mechanicals, connect to existing system for new office layout. See ap397208 sheet em101 comcheck energy compliance Date: April 17, 2012 Contractor: Hunter Mechanical Inc Permit type: Mechanical permit | Permit status: Completed | Completion date: August 13, 2013 | Permit id: 394486 | |||||
SCORE 99 Furnish and install duct, air devices and supplemental units for new office. Comcheck energy complaince ap397028 Date: April 20, 2012 Contractor: Hunter Mechanical Inc Permit type: Mechanical permit | Permit status: Completed | Completion date: July 31, 2012 | Permit id: 395083 | |||||
SCORE 100 Install (2) pantry sinks on 25th floor and one on the 24th floor Date: April 3, 2012 Contractor: Lees Plumbing Inc Permit type: Plumbing permit | Permit status: Completed | Completion date: July 31, 2012 | Permit id: 395490 | |||||
SCORE 96 Install 949 work area communication outlets, racks and patch panels, comm cabling between the 5 communication closets. Longest run 150" as per 2008 nec(commercial-office)(cc dist) Date: April 26, 2012 Contractor: Jw Carrigan Llc Permit type: Electrical permit | Permit status: Completed | Completion date: October 16, 2012 | Permit id: 396589 | |||||
SCORE 95 Furnish and install lighting, furniture feeds, occ sensors, poke throughs, and back boxed for tele data throughout space(commercial)(cc dist) Date: May 1, 2012 Contractor: Hatzel And Buehler Inc Permit type: Electrical permit | Permit status: Completed | Completion date: July 20, 2012 | Permit id: 397028 | |||||
SCORE 100 Install cat6 & coax to aprox(370)workstation on the 24th 25th fl,copper and fiber and coax riser cabling to the 42nd fl.& av cabling to tv locations to the 24th 25th floors. Installation to comply with articles 300. 21,770. 3 & 8 of the 2008 nec. Date: May 11, 2012 Contractor: Bluestone Communications Inc Permit type: Electrical permit | Permit status: Completed | Completion date: September 19, 2012 | Permit id: 397388 | |||||
SCORE 100 Relocation of 6 sprinkler heads to accommodate new ceilings Date: April 5, 2012 Contractor: Independence Fire Sprinkler Co Permit type: Suppression permit | Permit status: Completed | Completion date: September 4, 2012 | Permit id: 397879 | |||||
Interior alterations as per plans. Date: May 9, 2012 Permit type: Alteration permit | Permit status: Completed | Completion date: February 15, 2013 | Permit id: 402957 | |||||
SCORE 100 Relocate 12 diffusers Date: May 8, 2012 Contractor: Lormar Mechanical Services Permit type: Mechanical permit | Permit status: Completed | Completion date: December 14, 2012 | Permit id: 403652 | |||||
SCORE 100 Relocating 1078 sprinklers on floors 8-12 Date: March 16, 2012 Contractor: Oliver Sprinkler Co Inc Permit type: Suppression permit | Permit status: Completed | Completion date: July 31, 2012 | Permit id: 393933 | |||||
SCORE 100 Relocate 341 existing sprinkler heads on 24th & 25th floor. Date: March 19, 2012 Contractor: A And S Sprinkler Co Inc Permit type: Suppression permit | Permit status: Completed | Completion date: July 31, 2012 | Permit id: 394197 | |||||
SCORE 100 Alteration of mixed use office space. 6th floor: relocate4 horn existing horn strobes. 4th floor: add 4 new nhorn strobe devices as per nfpa72 Date: December 31, 2015 Contractor: Wm Aj Shaeffers Sons Inc Permit type: Electrical permit | Permit status: Completed | Completion date: March 1, 2017 | Permit id: 654411 | |||||
SCORE 100 Add 6 horn strobes per nfpa 72 (office space) Date: December 31, 2015 Contractor: Wm Aj Shaeffers Sons Inc Permit type: Electrical permit | Permit status: Expired | Completion date: December 31, 2015 | Permit id: 655633 | |||||
SCORE 100 Alterations to the hvac system as per plans Date: March 19, 2007 Contractor: Cms Mechanical Inc Permit type: Mechanical permit | Permit status: Completed | Completion date: July 30, 2007 | Permit id: 61995 | |||||
SCORE 96 Furnish and install 16 voice and 16 data cables cat5e (cc dist) Date: March 14, 2007 Contractor: James Carrigan Inc Permit type: Electrical permit | Permit status: Expired | Completion date: March 14, 2007 | Permit id: 62163 | |||||
SCORE 100 Install pantry sink Date: June 29, 2015 Contractor: Lees Plumbing Inc Permit type: Plumbing permit | Permit status: Completed | Completion date: October 6, 2015 | Permit id: 618510 | |||||
SCORE 86 Furnish and install cat5e cabling to 18 locations for data drops. Length of longest cable run = 155 ft. (cc dist) Date: March 13, 2007 Contractor: Multiphase Technologies Permit type: Electrical permit | Permit status: Expired | Completion date: March 13, 2007 | Permit id: 61755 | |||||
Interior demo & alterations ,fit out, finishes, floor layout new rooms, partitions, mill work, fit outs 6th & 14th floors. No change in use-occupancy, Date: October 5, 2015 Permit type: Alteration permit | Permit status: Completed | Completion date: March 1, 2016 | Permit id: 640683 | |||||
SCORE 100 Install (4) receptacles per 2008 nec (office space)cc district Date: October 22, 2015 Contractor: Wm Aj Shaeffers Sons Inc Permit type: Electrical permit | Permit status: Expired | Completion date: October 22, 2015 | Permit id: 646919 | |||||
SCORE 100 Relocae (25) 2x4s and (10) furniture feeds. Install (6) occ sensors and (8) receptacles per 2008 nec (office space)cc district Date: October 22, 2015 Contractor: Wm Aj Shaeffers Sons Inc Permit type: Electrical permit | Permit status: Completed | Completion date: December 30, 2015 | Permit id: 646922 | |||||
SCORE 100 Adding two kitchen sinks with associated water supply and drain piping back to mains and stacks. The installation will comply with the philadelphia plumbing code 2004 Date: October 26, 2015 Contractor: A T Chadwick Permit type: Plumbing permit | Permit status: Completed | Completion date: November 24, 2015 | Permit id: 647708 | |||||
SCORE 100 Adding 1 wc, 1 lav sink 1 ks with associated water supply and drain piping back to mains and stacks. The installation will comply with the philadelphia plumbing code 2004 Date: October 26, 2015 Contractor: A T Chadwick Permit type: Plumbing permit | Permit status: Completed | Completion date: January 22, 2016 | Permit id: 647715 | |||||
SCORE 95 Relocate 5 sprinklers on the 1st floor, 34 sprinklers on the 6th floor, 12 sprinklers on the 14th floor Date: October 29, 2015 Contractor: S A Comunale Co Inc Permit type: Suppression permit | Permit status: Completed | Completion date: February 24, 2016 | Permit id: 648715 | |||||
SCORE 100 Relocate 16 diffusers. Date: March 27, 2007 Contractor: Cms Mechanical Inc Permit type: Mechanical permit | Permit status: Completed | Completion date: September 17, 2007 | Permit id: 64923 | |||||
SCORE 98 Tenant fit-out no structual work. Date: March 26, 2007 Contractor: Patriot Construction Inc Permit type: Alteration permit | Permit status: Completed | Completion date: September 17, 2007 | Permit id: 60961 | |||||
SCORE 95 Add 38 dupl recepts, 5 quad recepts, 2 dedicated dupl recepts, 2 gfi recepts, remove existing lighting and replace with 38 2x4s. 13 down lights. Fire alarm system.(cc dist) Date: April 27, 2007 Contractor: Hatzel And Buehler Inc Permit type: Electrical permit | Permit status: Completed | Completion date: August 13, 2007 | Permit id: 61007 | |||||
SCORE 100 Install 124 plenum category 6 cables throughout suite Date: June 12, 2015 Contractor: Belles Electrical Contractors Permit type: Electrical permit | Permit status: Completed | Completion date: March 16, 2017 | Permit id: 609326 | |||||
SCORE 95 Add 3-furniture feeds, rework existing lighting layout remove & replace existing exit lights & add 6-duplex receptacles as per nec 2008 cc district (office bldg) Date: June 19, 2015 Contractor: Hatzel And Buehler Inc Permit type: Electrical permit | Permit status: Completed | Completion date: November 4, 2015 | Permit id: 606440 | |||||
SCORE 100 For partial demolition and construction of new non-bearing partitions to create new room configurations in an existing office building as per approved plans. No change in occupancy classification separate permits required for electrical, mechanical, plumbing and fire suppression systems. Date: April 2, 2015 Contractor: Bittenbender Construction Lp Permit type: Alteration permit | Permit status: Completed | Completion date: October 20, 2015 | Permit id: 597456 | |||||
SCORE 99 Reset existing diffusers in new existing ceiling grid Date: April 15, 2015 Contractor: Oreland Sheet Metal Co Permit type: Mechanical permit | Permit status: Completed | Completion date: November 24, 2015 | Permit id: 602934 | |||||
SCORE 100 Relocate (19) sprinkler heads to accommodate tenant layout as per all nfpa no. 13 and local codes. Date: April 20, 2015 Contractor: A And S Sprinkler Co Inc Permit type: Suppression permit | Permit status: Completed | Completion date: October 20, 2015 | Permit id: 603026 | |||||
SCORE 99 Relocate 21 diffusers in new grid system on the 43rd floor. Ez permit ductwork & warm-air appliances- for the installation of new ductwork, registers grilles diffusers, and warm-air appliances as per attached standard. Deviations from this standard will result in permit revocation and require submission of construction plans. Date: April 23, 2015 Contractor: Oreland Sheet Metal Co Permit type: Mechanical permit | Permit status: Completed | Completion date: October 20, 2015 | Permit id: 604997 | |||||
SCORE 100 Test and verify 2 cat 5e plenum cables (275 ft). Install 90- cat5e plenum cables (250ft). Test label cabling in rack, support new cabling, install wireless access pts, 1 new plenum patch cords in idf & station end.... In accordance with 2008 nec (hi-rise office) Date: April 18, 2017 Contractor: Bluestone Communications Inc Permit type: Electrical permit | Permit status: Expired | Completion date: April 18, 2017 | Permit id: 774897 | |||||
SCORE 100 Interior alterations as per plans. Date: March 3, 2009 Contractor: Structure Tone,Inc Permit type: Alteration permit | Permit status: Expired | Completion date: August 16, 2009 | Permit id: 198196 | |||||
SCORE 100 Install fire alarm notification devices, booster panel, lighting, controls & power to office furniture. Date: August 10, 2010 Contractor: H B Frazer Co Penna Permit type: Electrical permit | Permit status: Completed | Completion date: December 7, 2010 | Permit id: 289791 | |||||
SCORE 100 "interior alterations for new offices within existing tenant space." permit to include the construction of partitions (iebc level ii) to create office space within an existing b use on the seventh floor. Additional work to remaining space (level i) separate permits required for plumbing, electrical, mechanical, and fire suppression work. Date: July 19, 2010 Contractor: Frank R Lamarra Builders And Con Permit type: Alteration permit | Permit status: Completed | Completion date: August 18, 2010 | Permit id: 289977 | |||||
SCORE 100 Relocate existing sprinkler heads (4th, 5th and 6th floors) Date: August 12, 2010 Contractor: A And S Sprinkler Co Inc Permit type: Suppression permit | Permit status: Completed | Completion date: May 1, 2011 | Permit id: 295908 | |||||
SCORE 100 Relocate 5 existing sprinkler heads (7th floor) Date: August 12, 2010 Contractor: A And S Sprinkler Co Inc Permit type: Suppression permit | Permit status: Completed | Completion date: August 18, 2010 | Permit id: 295985 | |||||
SCORE 100 Interior alterations for office building. Detail and locations show on the submitted plans. Date: September 2, 2010 Contractor: Frank R Lamarra Builders And Con Permit type: Alteration permit | Permit status: Completed | Completion date: November 12, 2010 | Permit id: 297735 | |||||
SCORE 100 F i cat5e plenum rated cables, installation to comply with articles 300. 21, 300. 22 & 8 of the 2008 nec. Date: February 19, 2015 Contractor: Gt Telecom Permit type: Electrical permit | Permit status: Completed | Completion date: November 2, 2015 | Permit id: 591074 | |||||
SCORE 100 Fast form building permit Date: March 1, 2007 Contractor: Oliver Sprinkler Co Inc Permit status: Completed | Completion date: June 20, 2008 | Permit id: 59159 | |||||
SCORE 100 (o) sk (1) fx Date: March 5, 2007 Contractor: Lees Plumbing Inc Permit type: Plumbing permit | Permit status: Completed | Completion date: June 2, 2008 | Permit id: 59362 | |||||
SCORE 100 Provide and install cat6 plenum rated cables,(longest 100)all cabling will be installed in j-hooks,all penetrations will be fire stopped as per 2008 nec (cc district) Date: April 30, 2015 Contractor: Lanconnect Inc Permit type: Electrical permit | Permit status: Completed | Completion date: August 23, 2016 | Permit id: 597092 | |||||
SCORE 99 Relocate (11) diffusers Date: December 2, 2010 Contractor: Oreland Sheet Metal Co Permit type: Mechanical permit | Permit status: Completed | Completion date: May 1, 2011 | Permit id: 314599 | |||||
SCORE 100 Installation of a pantry sink Date: December 9, 2010 Contractor: Lees Plumbing Inc Permit type: Plumbing permit | Permit status: Completed | Completion date: May 1, 2011 | Permit id: 315327 | |||||
SCORE 100 Relocate 82 existing sprinkler heads(commercial) Date: January 19, 2011 Contractor: A And S Sprinkler Co Inc Permit type: Suppression permit | Permit status: Completed | Completion date: August 15, 2011 | Permit id: 321300 | |||||
SCORE 100 Interior non-load bearing demolition and debris removal (10th and 12th floors) Date: April 21, 2011 Contractor: Cippco Contracting Inc Permit type: Demolition permit | Permit status: Completed | Completion date: July 7, 2011 | Permit id: 337103 | |||||
SCORE 100 Install new sheetmetal ductwork system per plan. Date: June 13, 2011 Contractor: Wm J Donovan Co Permit type: Mechanical permit | Permit status: Completed | Completion date: June 24, 2011 | Permit id: 339497 | |||||
SCORE 100 Replace existing lighting: wire new lighting controls, wire new walls and office partitions as per 2008 nec add new fire alarm speaker strobes as per nfpa72 (cc district) Date: December 1, 2010 Contractor: H B Frazer Co Penna Permit type: Electrical permit | Permit status: Completed | Completion date: January 20, 2011 | Permit id: 306723 | |||||
SCORE 100 Relocate 15 diffusers Date: October 21, 2010 Contractor: Lormar Mechanical Services Permit type: Mechanical permit | Permit status: Completed | Completion date: April 25, 2011 | Permit id: 307560 | |||||
SCORE 100 Interior alterations as per plan. Date: November 10, 2010 Contractor: Sullivan Company The Permit type: Alteration permit | Permit status: Completed | Completion date: May 1, 2011 | Permit id: 309539 | |||||
SCORE 100 Relocate (20) diffusers Date: November 8, 2010 Contractor: Lormar Mechanical Services Permit type: Mechanical permit | Permit status: Completed | Completion date: December 17, 2010 | Permit id: 310427 | |||||
SCORE 100 Relocate 34 existing sprinkler heads (3rd floor) Date: November 17, 2010 Contractor: A And S Sprinkler Co Inc Permit type: Suppression permit | Permit status: Completed | Completion date: December 17, 2010 | Permit id: 312144 | |||||
SCORE 100 Relocation of sprinkler heads Date: November 22, 2010 Contractor: Independence Fire Sprinkler Co Permit type: Suppression permit | Permit status: Completed | Completion date: May 1, 2011 | Permit id: 312977 | |||||
SCORE 100 Selective interior demolition of non load bearing assemblies Date: October 23, 2013 Contractor: Sullivan Company The Permit type: Demolition permit | Permit status: Completed | Completion date: April 22, 2014 | Permit id: 501961 | |||||
SCORE 86 Instal (33) cat 5e data cables, jacks and plates from telecommunications closet to new locations in office space - furthest cable= 235 ft. As per nec 2005 Date: February 6, 2007 Contractor: Multiphase Technologies Permit type: Electrical permit | Permit status: Expired | Completion date: February 28, 2007 | Permit id: 54858 | |||||
SCORE 100 Relocate (24) existing sprinkler heads in order to accommodate tenant as per nfpa no. 13 and local codes. Date: June 12, 2014 Contractor: A And S Sprinkler Co Inc Permit type: Suppression permit | Permit status: Completed | Completion date: July 25, 2014 | Permit id: 542547 | |||||
SCORE 95 Re-configure 23-2x2 lights, 7-switches, 2-furniture feeds & 17-recepts to accommodate new layouts as per nec 2008 (office bldg) cc district Date: June 18, 2014 Contractor: Hatzel And Buehler Inc Permit type: Electrical permit | Permit status: Completed | Completion date: September 6, 2014 | Permit id: 543890 | |||||
SCORE 100 6 new fire alarm devices,5 relocate existing alarm devices as per 2008 nec and nfpa72 (multi story offices) Date: September 6, 2012 Contractor: Metro Electric Co Inc Permit type: Electrical permit | Permit status: Completed | Completion date: December 17, 2012 | Permit id: 425431 | |||||
SCORE 95 Install 15 new speaker strobes, 1 new smoke detector, remove & relocate 11 existing speaker strobes as per 2008 nec & nfpa 72 (office space) Date: October 22, 2012 Contractor: Hatzel And Buehler Inc Permit type: Electrical permit | Permit status: Completed | Completion date: December 12, 2012 | Permit id: 426121 | |||||
SCORE 100 Relocate 21-lighting, replace 5-lighting, 12-occupancy sensors, 11-duplex recepts & 9-quad recpts as per nec 2008 Date: October 9, 2012 Contractor: Metro Electric Co Inc Permit type: Electrical permit | Permit status: Completed | Completion date: December 7, 2012 | Permit id: 428974 | |||||
SCORE 100 Relocate 4 diffusers Date: September 27, 2012 Contractor: Lormar Mechanical Services Permit type: Mechanical permit | Permit status: Completed | Completion date: February 4, 2013 | Permit id: 429541 | |||||
SCORE 100 Replace exisiting light poles with new light poles reuse exisiting conduit and wiring 21 total lights per 2008 nec (office bldg) Date: September 28, 2012 Contractor: Carr And Duff Co Permit type: Electrical permit | Permit status: Completed | Completion date: January 8, 2016 | Permit id: 429590 | |||||
SCORE 100 Relocate 12 existing sprinkler heads to accommodate new tenant wall & ceiling layout as per all nfpa no. 13 and local codes (37th floor) Date: October 2, 2012 Contractor: A And S Sprinkler Co Inc Permit type: Suppression permit | Permit status: Completed | Completion date: January 24, 2013 | Permit id: 430476 | |||||
SCORE 100 Relocate (147) existing sprinkler heads - 33rd flr. Date: October 9, 2012 Contractor: A And S Sprinkler Co Inc Permit type: Suppression permit | Permit status: Completed | Completion date: April 15, 2013 | Permit id: 431512 | |||||
SCORE 100 Interior demolition of non-load bearing walls and millwork for futre reconfiguration of offices. Building built after 1981. No structural changes. Must maintain all code required fire rating on wall and floor ceiling assemblies. Three sets of plans drawn to professional quality are to be submitted for review and approval by the department before work on renovation starts. Date: October 11, 2012 Contractor: Sullivan Company The Permit type: Demolition permit | Permit status: Completed | Completion date: November 28, 2012 | Permit id: 432069 | |||||
SCORE 99 Relocate 4 supply diffusers on the 47th floor. Date: November 19, 2012 Contractor: Oreland Sheet Metal Co Permit type: Mechanical permit | Permit status: Completed | Completion date: December 28, 2012 | Permit id: 438734 | |||||
SCORE 100 Replace existing fixtures with new qty 34 install duplex receptacles qty 8 per 2008 nec (office bldg) Date: May 7, 2013 Contractor: Shelly Electric Co Inc Permit type: Electrical permit | Permit status: Expired | Completion date: July 12, 2013 | Permit id: 469581 | |||||
SCORE 100 Relocate (12) diffusers Date: May 14, 2013 Contractor: Lormar Mechanical Services Permit type: Mechanical permit | Permit status: Completed | Completion date: August 10, 2013 | Permit id: 471096 | |||||
SCORE 100 Relocate 15 diffusers Date: February 6, 2015 Contractor: Lormar Mechanical Services Permit type: Mechanical permit | Permit status: Completed | Completion date: July 15, 2015 | Permit id: 589106 | |||||
SCORE 100 Installation of (2) pantry sinks, connect to existing sanitary, vent and domestic water Date: February 12, 2015 Contractor: Lormar Mechanical Services Permit type: Plumbing permit | Permit status: Completed | Completion date: July 15, 2015 | Permit id: 589897 | |||||
SCORE 100 Relocate 21 existing sprinkler heads (commercial) Date: February 12, 2015 Contractor: A And S Sprinkler Co Inc Permit type: Suppression permit | Permit status: Completed | Completion date: July 15, 2015 | Permit id: 590204 | |||||
SCORE 100 Relocate existing sprinkler heads (commercial) Date: February 12, 2015 Contractor: A And S Sprinkler Co Inc Permit type: Suppression permit | Permit status: Completed | Completion date: June 5, 2015 | Permit id: 590205 | |||||
SCORE 95 Install 10-speaker strobes as per nec 2008 & nfpa 72 (office bldg) cc district Date: December 30, 2014 Contractor: Hatzel And Buehler Inc Permit type: Electrical permit | Permit status: Completed | Completion date: August 23, 2016 | Permit id: 574558 | |||||
SCORE 100 Relocate 22 existing sprinkler heads. Date: November 18, 2014 Contractor: A And S Sprinkler Co Inc Permit type: Suppression permit | Permit status: Completed | Completion date: April 8, 2015 | Permit id: 574976 | |||||
SCORE 100 Relocate 27 sprinklers in the 14th floor Date: July 17, 2014 Contractor: Oliver Sprinkler Co Inc Permit type: Suppression permit | Permit status: Completed | Completion date: October 15, 2014 | Permit id: 549883 | |||||
SCORE 95 Relocate (2) speaker strobes as per 2008 nec Date: January 5, 2011 Contractor: Hatzel And Buehler Inc Permit type: Electrical permit | Permit status: Completed | Completion date: August 8, 2012 | Permit id: 313830 | |||||
SCORE 100 New fire alarm booster panel and signalling devices,new light fixtures and lightind controls,branch power wiring in new walls and to furniture systems as per 2008 nec Date: March 23, 2011 Contractor: H B Frazer Co Penna Permit type: Electrical permit | Permit status: Completed | Completion date: May 2, 2011 | Permit id: 314443 | |||||
SCORE 100 Interior alterations per plan 2nd floor Date: December 14, 2010 Contractor: Frank R Lamarra Builders And Con Permit type: Alteration permit | Permit status: Completed | Completion date: June 24, 2011 | Permit id: 314479 | |||||
SCORE 100 Relocate exisiting sprinkler head(com) Date: October 21, 2016 Contractor: A And S Sprinkler Co Inc Permit type: Suppression permit | Permit status: Completed | Completion date: February 15, 2017 | Permit id: 730858 | |||||
SCORE 100 Install 5 new light fixtures, 1015 light switches, 1 light control panel, 214 recepts, 13 floor recepts, 14 hvac power, 1 - 208 208 volt panel, 1 - 45kvw transformer as per 2008 nec (cc district) no fire alarm Date: December 6, 2016 Contractor: New Light Electric Inc Permit type: Electrical permit | Permit status: Completed | Completion date: March 13, 2017 | Permit id: 732263 | |||||
SCORE 99 Alterations to existing hvac system to include furnish and install duct, air devices, (2) exhaust fans, (1) supplemental hvac unit & control vav boxes for new office layout on 35th floor as per approved plans. Date: November 7, 2016 Contractor: Hunter Mechanical Inc Permit type: Mechanical permit | Permit status: Completed | Completion date: February 15, 2017 | Permit id: 733416 | |||||
SCORE 100 Installation of 2- sinks, 2- open site drains and 2- 6 gallon water heaters Date: November 8, 2016 Contractor: Lormar Mechanical Services Permit type: Plumbing permit | Permit status: Completed | Completion date: February 15, 2017 | Permit id: 733818 | |||||
SCORE 100 Furnish and install 164 category 6 plenum cables average cable pull 1 feet per 2008 nec (office space) Date: January 11, 2017 Contractor: Belles Electrical Contractors Permit type: Electrical permit | Permit status: Expired | Completion date: January 11, 2017 | Permit id: 739977 | |||||
SCORE 100 No change in use and occupancy classification. Level ii interior alterations on the 17th, 19th, 20th & 22nd floors. Separate permit required for any mep and fire suppression work. Date: December 14, 2016 Contractor: Hunter Roberts Construction Gr Permit type: Alteration permit | Permit status: Completed | Completion date: April 27, 2017 | Permit id: 741246 | |||||
SCORE 100 Relocate (20) existing sprinkler heads in order to accommodate tenant layouts as per nfpa no. 13 and all local codes. Date: December 15, 2016 Contractor: A And S Sprinkler Co Inc Permit type: Suppression permit | Permit status: Completed | Completion date: April 17, 2017 | Permit id: 743995 | |||||
SCORE 95 Furnish 17 lighting fixtures, revise existing switches, & sensors, (6 furniture feeds) & 21 recepts, re use existing panels, nminor revisions as per 2008 nec (cc district) Date: January 24, 2017 Contractor: Hatzel And Buehler Inc Permit type: Electrical permit | Permit status: Completed | Completion date: April 11, 2017 | Permit id: 745448 | |||||
SCORE 100 Provide and install 1 cat6 plenum cable to locations @1 average. All cabling will be installed in j-hooks per nec 2008. All penetrations will be fire stopped er nec 2008. Date: December 30, 2016 Contractor: Lanconnect Inc Permit type: Electrical permit | Permit status: Expired | Completion date: December 30, 2016 | Permit id: 746961 | |||||
SCORE 100 Relocate 12 heads Date: March 14, 2013 Contractor: Majek Fire Protection, Inc Permit type: Suppression permit | Permit status: Completed | Completion date: May 28, 2013 | Permit id: 459025 | |||||
SCORE 100 Relocate 9-fire alarm devices, no new wiring required, connect to existing fire alarm panel circuitry as per nec 2008 & nfpa 72 (comm) Date: March 26, 2013 Contractor: Metro Electric Co Inc Permit type: Electrical permit | Permit status: Expired | Completion date: March 26, 2013 | Permit id: 459622 | |||||
SCORE 100 Relocate 9 existing devices to new location add new devices,no new panel,annunicators and booster per 2008 nec & nfpa 72(office bldg) Date: February 19, 2014 Contractor: Mirarchi Brothers Inc Permit type: Electrical permit | Permit status: Completed | Completion date: November 25, 2014 | Permit id: 510815 | |||||
SCORE 100 Construction of non demising, interior, non bearing partitions to create new offices on the 46th floor. Fire rated assemblies are required to be maintainrd at all times. Electrical, telecommunications, plumbing, mechanical, and fire suppression work requires additional permits. Call the inspector prior to starting work. Date: January 6, 2012 Contractor: Sullivan Company The Permit type: Alteration permit | Permit status: Completed | Completion date: November 2, 2012 | Permit id: 379355 | |||||
SCORE 95 Office space-furnish & install fire alarm as per 2008 nec (cc district) Date: March 15, 2012 Contractor: Hatzel And Buehler Inc Permit type: Electrical permit | Permit status: Completed | Completion date: August 14, 2012 | Permit id: 380226 | |||||
SCORE 95 Furnish and install lighting an power throughout(commercial)(cc dist)(46th floor only) Date: January 9, 2012 Contractor: Hatzel And Buehler Inc Permit type: Electrical permit | Permit status: Completed | Completion date: May 31, 2012 | Permit id: 382140 | |||||
SCORE 100 Demo of non bearing walls, ceilings and flooring for office space. Date: January 12, 2012 Contractor: Sullivan Company The Permit type: Demolition permit | Permit status: Completed | Completion date: March 12, 2012 | Permit id: 382933 | |||||
SCORE 100 Interior demolition of interior, non load bearing assemblies at floors 8 thru 12 only. Date: January 26, 2012 Contractor: Structure Tone,Inc Permit type: Demolition permit | Permit status: Completed | Completion date: March 30, 2012 | Permit id: 383449 | |||||
SCORE 100 Relocate 24 sprinklers on the 46th floor Date: January 20, 2012 Contractor: Oliver Sprinkler Co Inc Permit type: Suppression permit | Permit status: Completed | Completion date: November 2, 2012 | Permit id: 383956 | |||||
SCORE 100 Amdin permit to amend #366012 as per plans Date: March 26, 2012 Contractor: Hunter Roberts Construction Gr Permit type: Administrative permit | Permit status: Completed | Completion date: July 11, 2012 | Permit id: 384489 | |||||
SCORE 100 Furnish & install 64 category 5e, plenum cables, longest run 125, install paging system as per 2008 nec (office bldg) Date: September 21, 2012 Contractor: Gt Telecom Permit type: Electrical permit | Permit status: Completed | Completion date: January 15, 2013 | Permit id: 424879 | |||||
SCORE 100 Relocation of 1 spr heads Date: August 30, 2012 Contractor: Independence Fire Sprinkler Co Permit type: Suppression permit | Permit status: Completed | Completion date: December 14, 2012 | Permit id: 424885 | |||||
SCORE 98 Interior renovation of cafe as per plans. No facade work. Date: September 5, 2012 Contractor: Patriot Construction Inc Permit type: Alteration permit | Permit status: Completed | Completion date: March 4, 2013 | Permit id: 425055 | |||||
SCORE 100 Interior demolition of non-bearing partitions on the 40th floor only. Date: November 26, 2014 Contractor: Cippco Contracting Inc Permit type: Demolition permit | Permit status: Completed | Completion date: February 24, 2015 | Permit id: 576598 | |||||
SCORE 100 Installation of pantry sink- connect to existing sanitary, vent and water Date: December 2, 2014 Contractor: Lormar Mechanical Services Permit type: Plumbing permit | Permit status: Completed | Completion date: April 9, 2015 | Permit id: 576966 | |||||
SCORE 95 Re-work and re-use devices,adding 6 new devices to space as per nfpa72 (cc district) Date: January 8, 2015 Contractor: Hatzel And Buehler Inc Permit type: Electrical permit | Permit status: Completed | Completion date: May 28, 2015 | Permit id: 577446 | |||||
SCORE 100 Provide and install cat6 plenum cables,(longest 125)all cabling will be installed in j-hooks,all penetrations will be fire stopped per 2008 nec (office space) Date: December 4, 2014 Contractor: Lanconnect Inc Permit type: Electrical permit | Permit status: Completed | Completion date: October 28, 2015 | Permit id: 577673 | |||||
SCORE 100 Install 3-fire alarm system speaker strobe devices as per nfpa 72 cc district Date: December 26, 2014 Contractor: Metro Electric Co Inc Permit type: Electrical permit | Permit status: Completed | Completion date: April 23, 2015 | Permit id: 578892 | |||||
SCORE 100 Installation of 2 sinks-the installation will comply with the philadelphia plumbing code 2004 Date: December 16, 2014 Contractor: Lees Plumbing Inc Permit type: Plumbing permit | Permit status: Completed | Completion date: March 18, 2015 | Permit id: 579149 | |||||
Interior alterations to 14th floor as per plans. Separate permits required for mep and fire suppression work. Date: January 8, 2015 Permit type: Alteration permit | Permit status: Completed | Completion date: June 26, 2015 | Permit id: 581489 | |||||
SCORE 100 Installation of a pantry sink Date: January 20, 2015 Contractor: Lees Plumbing Inc Permit type: Plumbing permit | Permit status: Completed | Completion date: April 7, 2015 | Permit id: 584090 | |||||
SCORE 100 Remove and replace 33 existing light fixtures per 2008 nec (office bldg) Date: January 16, 2015 Contractor: Metro Electric Co Inc Permit type: Electrical permit | Permit status: Expired | Completion date: January 16, 2015 | Permit id: 584962 | |||||
SCORE 100 Relocate (20) registers diffusers Date: January 18, 2007 Contractor: Lormar Mechanical Services Permit type: Mechanical permit | Permit status: Completed | Completion date: April 18, 2007 | Permit id: 50499 | |||||
SCORE 100 Install kitchen sink, open site drain, water heater, extend from existing sanitary and domestic water Date: December 8, 2017 Contractor: Lormar Mechanical Services Permit type: Plumbing permit | Permit status: Active | Completion date: December 8, 2017 | Permit id: 836694 | |||||
SCORE 100 Relocate 21 existing sprinkler heads (commercial) Date: December 5, 2017 Contractor: A And S Sprinkler Co Inc Permit type: Suppression permit | Permit status: Active | Completion date: December 5, 2017 | Permit id: 836881 | |||||
SCORE 100 Ez permit ductwork & warm-air appliances- for the installation if new ductwork, registers grilles diffusers, and warm-air appliances as per attached standards. Deviations from these standards require submission of construction and site plans. Relocate (19) diffusers, to comply with ez permit standards for ductwork. Date: December 4, 2017 Contractor: Lormar Mechanical Services Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit type: Mechanical permit | Permit status: Active | Completion date: December 4, 2017 | Permit id: 836384 | |||||
Electrical permit Date: July 9, 2014 Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit status: Completed | Permit id: 540839 | |||||
Mechanical permit Date: July 9, 2014 Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit status: Completed | Permit id: 545982 | |||||
Alteration permit Date: January 26, 2015 Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit status: Completed | Permit id: 584936 | |||||
Mechanical permit Date: January 12, 2017 Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit status: Active | Permit id: 749514 | |||||
Administrative permit Date: February 20, 2013 Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit status: Completed | Permit id: 454016 | |||||
Mechanical permit Date: January 30, 2015 Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit status: Completed | Permit id: 585605 | |||||
Mechanical permit Date: July 23, 2013 Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit status: Completed | Permit id: 484797 | |||||
Demolition permit Date: August 18, 2016 Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit status: Completed | Permit id: 715934 | |||||
Electrical permit Date: March 18, 2013 Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit status: Completed | Permit id: 453463 | |||||
Suppression permit Date: July 29, 2013 Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit status: Completed | Permit id: 485892 | |||||
Alteration permit Date: July 7, 2014 Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit status: Completed | Permit id: 545603 | |||||
Alteration permit Date: February 6, 2013 Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit status: Completed | Permit id: 451015 | |||||
Plumbing permit Date: November 24, 2014 Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit status: Completed | Permit id: 575922 | |||||
Administrative permit Date: February 12, 2014 Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit status: Completed | Permit id: 519436 | |||||
Electrical permit Date: March 11, 2015 Client: Brandywine Operating Partners Lp | Client Company: Brandywine Realty Trust | Permit status: Completed | Permit id: 590125 |